Programme status key
| Description |
Status |
| SCHEME PROGRAMMED TO BE DELIVERED - ( Approximate duration and START month indicated ) |
Scheduled |
| SCHEME UNDERWAY - WORK IN PROGRESS - (Traffic Management as required, during works) |
In progress |
| WORKS ONSITE SUBSTANTIALLY COMPLETE. ( Road Markings and White Lining - Weather permitting ) |
Complete |
Last updated - 10th October 2025
Mid Argyll
Mid Argyll - bituminous surfacing
| Location |
Treatment type |
Duration - days |
Start month |
Status |
| A819 Electric Cottage PH 5 Widening and Drainage |
Structural |
30 |
July |
In progress |
| A816 Rhudle Mill straight |
Overlay |
5 |
May |
In progress |
| B841 Cairnbaan bridge -A816 junction |
Inlay |
5 |
May |
Complete |
| B8025 Bellanoch - Barluagan Junction - Pre SD (Future yrs) |
Edge/Overlay |
15 |
May |
Complete |
| B8025 Bellanoch between bridges Pre-SD (Future years) |
Patching |
2 |
May |
Complete |
| A819 Structural Patching |
Patching |
15 |
July |
Complete |
| Ardrishaig - West Canal Rd |
Overlay |
3 |
June |
Complete |
| Crinan - Above canal car park Pre-SD Future Years |
Patching |
2 |
June |
Complete |
| Ardrishaig - Lock 4 Bridge deck - road surface |
Surface Seal |
5 |
Nov |
Scheduled |
| B8025 Bellanoch Bridge deck - road surface |
Surface Seal |
4 |
Nov |
Scheduled |
Kintyre
Kintyre - bituminous surfacing
| Location |
Treatment type |
Duration - days |
Start month |
Status |
| B842 Stewarton Junction |
Inlay |
3 |
June |
Complete |
| Campbeltown - New Quay St onto Kilkerran Rd |
Inlay |
5 |
June |
Complete |
| Campbeltown - Stewart Rd |
Inlay |
3 |
June |
Complete |
| Campbeltown - Saint John Street |
Inlay |
3 |
June |
Complete |
| C19 Glenramskil/Kilkerran road Pre SD ( Future years) |
Patching |
3 |
Aug |
Complete |
| Campbeltown - C19 Argyll Street |
Inlay |
3 |
July |
Complete |
| Campbeltown - Fort Argyll Road/Keith Crescent |
Inlay |
5 |
Aug |
Complete |
| Campbeltown - Glebe Street |
Inlay |
3 |
Aug |
Complete |
| UC17 Tangy (Inc drainage improvements) |
Overlay |
6 |
Sept |
Complete |
| (C20) Glenbarr cottages PreSD (Future years) |
Patching |
5 |
Aug |
Complete |
| C20 Glenbarr PreSD ( Future Years) |
Patching |
5 |
Aug |
Complete |
| Dalsmirren Rd. - Edge Strengthening |
Structural |
14 |
Sept |
In progress |
Islands
Islands - bituminous surfacing
| Location |
Treatment type |
Duration - days |
Start month |
Status |
| ISLAY A847 - Port Charlotte, Hotel |
Inlay 2 layers |
4 |
June |
Scheduled |
| ISLAY A847 - Port Ellen to B8016 junction |
Patching |
2 |
June |
Scheduled |
| ISLAY A847 - Bruichladdich |
Inlay 2 layers |
3 |
Feb 26 |
Scheduled |
| ISLAY C17 - Emeraval to Kilnaughton |
Overlay |
3 |
June |
Complete |
| ISLAY A846 - Port Ellen School - Traffic Calming |
Inlay 2 layers |
3 |
June |
Complete |
| ISLAY UC25 Emeraval link road |
Overlay |
2 |
June |
Complete |
| ISLAY B8016 - High Road, N & S of Laggan bridge |
Patching |
5 |
Aug |
Complete |
| ISLAY B8016 - South of Glenegadale |
Machine Patch |
7 |
Aug |
Complete |
| COLONSAY - B8085 South Road (jetpatcher ) |
Patching |
5 |
Mar 26 |
Scheduled |
| JURA - A846 - Ardmenish flats |
Overlay |
10 |
Sept |
Complete |
| JURA - A846 - selective Improvements |
Overlay |
5 |
Feb 26 |
Scheduled |
| Islay - A846 Bunanuisg to Cruach Rd - additional treatment |
Thin Overlay |
10 |
May |
Complete |