Mid Argyll, Kintyre and the Islands bituminous surfacing scheme 2026/27

Programme status key
Description Status
SCHEME PROGRAMMED TO BE DELIVERED - ( Approximate duration and START month indicated ) Scheduled
SCHEME UNDERWAY - WORK IN PROGRESS -  (Traffic Management as required, during works) In progress
WORKS ONSITE SUBSTANTIALLY COMPLETE. ( Road Markings and White Lining - Weather permitting ) Complete

Last updated - 1st May 2026

Mid Argyll

Location Treatment type Duration (Days) Start Month Status
A819 North Tullich - Drimfern  Inlay 7 JUNE Scheduled
A816 Acharonich Inlay 5 JULY Scheduled
B841 Dunadry - Road Realignment re-align & widen 20 OCT Scheduled
B8014 South Tiretigan  Inlay 5 JULY Scheduled
B8014 South Tiretigan Ph2  Inlay 5 JULY Scheduled
B8024 West of Dunmore School House  Inlay 3 JULY Scheduled
U24 Barrananoill Road  Inlay 3 OCT Scheduled

Kintyre

Location Treatment type Duration (Days) Start month Status
C 18  Dalsmirren Edge Strengthening Edge Strengthen 25 OCT Scheduled
U31  Kirk Street Inlay 3 AUG  Scheduled
C19 Argyll Street Inlay 2 AUG  Scheduled
C19 Kilkerran Road Pre SD Overlays  2 AUG  Scheduled
U26 Hillside Road Inlay 4 AUG  Scheduled
U9 Calton Avenue Inlay 2 AUG  Scheduled
U 17 Davaar Avenue Inlay 5 AUG  Scheduled
C22 / U52 Isle of Gigha  Overlays  5 AUG  Scheduled

Islands

Location Treatment type Duration (Days) Start month Status
A846  Isle of Jura - Defferred Set Overlay 15 AUG  Scheduled
A847 - Islay - South of Port Charlotte  Overlay 10 AUG  Scheduled
A846 Laphroaig   Grid / Asphalt / Deferred Structural  10 JUNE Scheduled