Programme status key
| Description |
Status |
| SCHEME PROGRAMMED TO BE DELIVERED - ( Approximate duration and START month indicated ) |
Scheduled |
| SCHEME UNDERWAY - WORK IN PROGRESS - (Traffic Management as required, during works) |
In progress |
| WORKS ONSITE SUBSTANTIALLY COMPLETE. ( Road Markings and White Lining - Weather permitting ) |
Complete |
Last updated - 1st May 2026
Bute
| Location |
Treatment type |
Duration (Days) |
Start month |
Status |
| A844 Miekle Kilchattten to Culvene |
Overlay |
10 |
MAY |
Scheduled |
| C3 Plan Road. Contunation to road end |
Overlay |
6 |
JUNE |
Scheduled |
| A844 Greenwood crossing to Acholter bridge |
Overlay |
8 |
JUNE |
Scheduled |
| A844 Kilmory circle- Quogoch to Kerryfearn |
Overlay |
10 |
JUNE |
Scheduled |
Cowal
| Location |
Treatment type |
Duration (Days) |
Start Month |
Status |
| A886 Leanach |
Overlay |
5 |
JULY |
Scheduled |
| A886 Through Glendaruel |
Overlay |
10 |
JULY |
Scheduled |
| B8000 Shinty Brae |
Inlay |
8 |
JULY |
Scheduled |
| B8000 Various Sections - Rural |
Overlay |
8 |
JULY |
Scheduled |
| C10 Pol depot to Port Lammont |
Overlay |
10 |
AUG |
Scheduled |
| A815 Auchamore Road - Wellington St to Edward St |
Inlay |
10 |
AUG |
Scheduled |
| A885 Argyll street- Kirk Brae to John street |
Inlay |
12 |
AUG |
Scheduled |
| A815 Alexander Parade - John street to Queen street |
Inlay |
12 |
SEPT |
Scheduled |
| U29 George St Dunoon - John street to Queen street |
Inlay |
12 |
SEPT |
Scheduled |