Roads Capital Programme 2026/27

Strategic Surfacing Schemes

Programme status key
Description Status
SCHEME PROGRAMMED TO BE DELIVERED - ( Approximate duration and START month indicated ) Scheduled
SCHEME UNDERWAY - WORK IN PROGRESS -  (Traffic Management as required, during works) In progress
WORKS ONSITE SUBSTANTIALLY COMPLETE. ( Road Markings and White Lining - Weather permitting ) Complete

Last updated - 18th June 2026

Major surfacing schemes - overlay

Location Treatment type Duration (Days) Start Month Status
 A819  ELECTRIC COTTAGE PH6 - Final surface and lining  Overlay 15 JUNE Scheduled
A8003 NORTH OF TIGHNABRUAICH PH9 - Final surface and lining Overlay 10 OCT Scheduled
A817 HAUL ROAD Accident area - High PSV stone Overlay 20 OCT Scheduled
 ISLE OF JURA - DEFERRED SET MACADAM - Various locations Overlay 15 JULY Scheduled
 ISLE OF ISLAY - DEFERRED SET MACADAM - Various locations Overlay 30 AUG/SEPT Scheduled