Programme status key
| Description |
Status |
| SCHEME PROGRAMMED TO BE DELIVERED - ( Approximate duration and START month indicated ) |
Scheduled |
| SCHEME UNDERWAY - WORK IN PROGRESS - (Traffic Management as required, during works) |
In progress |
| WORKS ONSITE SUBSTANTIALLY COMPLETE. ( Road Markings and White Lining - Weather permitting ) |
Complete |
Last updated - 6th July 2026
Major surfacing schemes - overlay
| Location |
Treatment type |
Duration (Days) |
Start Month |
Status |
| A819 ELECTRIC COTTAGE PH6 - Final surface and lining |
Overlay |
15 |
JULY |
Scheduled |
| A8003 NORTH OF TIGHNABRUAICH PH9 - Final surface and lining |
Overlay |
10 |
OCT |
Scheduled |
| A817 HAUL ROAD Accident area - High PSV stone |
Overlay |
20 |
OCT |
Scheduled |
Isle of Islay - deferred set macadam
| Location |
Treatment type |
Duration (Days) |
Start Month |
Status |
| A847 Port Charlotte - Nerabus |
Overlay |
10 |
AUGUST |
Scheduled |
| A846 Laggan Bridge North (Corray Farm) |
Overlay |
10 |
AUGUST |
Scheduled |
| B8016 Leorin |
Overlay |
10 |
AUGUST |
Scheduled |
Isle of Jura - deferred set macadam
| Location |
Treatment type |
Duration (Days) |
Start Month |
Status |
| A846 West Adrfin |
Overlay |
3 |
JULY |
Scheduled |
| A846 Feolin Farm |
Overlay |
3 |
JULY |
Scheduled |
| A846 Leargybreck |
Overlay |
3 |
JULY |
Scheduled |
| A846 South of Lagg |
Overlay |
3 |
JULY |
Scheduled |