Roads Capital Programme 2026/27

Surface Dressing - All Areas

Programme status key
Description Status
SCHEME PROGRAMMED TO BE DELIVERED - ( Approximate duration and START month indicated ) Scheduled
SCHEME UNDERWAY - WORK IN PROGRESS -  (Traffic Management as required, during works) In progress
WORKS ONSITE SUBSTANTIALLY COMPLETE. ( Road Markings and White Lining - Weather permitting ) Complete

Last updated - 1st May 2026

Mid Argyll, Kintyre and the Islands

Mid Argyll Pre-surface dressing - preparation works

Location Duration (days) Start month Status
B8025 Moss 10 APR In Progress

Mid Argyll - Surface Dressing - binder and chip operations

Location Duration (days) Start month Status
B8025 Moss 1 JUNE Scheduled

Kintyre Pre-surface dressing - preparation works

Location Duration (days) Start month Status
Low Askomil 5 MAY Scheduled
Glenbarr Loop 5 MAY Scheduled
B843   Stewarton   -  Machrihanish  Phase 1 15 MAY Scheduled

Kintyre Surface Dressing - binder and chip operations

Location Duration (days) Start month Staus
Low Askomil 2 JUNE Scheduled
Glenbarr Loop 2 JUNE Scheduled
B843   Stewarton   -  Machrihanish     ph 1 4 JUNE Scheduled

Mid Argyll, Kintyre and the Islands Pre-surface dressing 2027/28

Location Duration (days Start month Staus
Various locations in MAKI  20 OCT Scheduled

Bute and Cowal

Bute - Pre-surface dressing - preparation works

Location Duration (days) Start month Status
A844 Cranslagvourity 5 MAY Scheduled

Bute - Surface dressing - binder and chip operations

Location Duration (days) Start month Status
A844 Cranslagvourity 2 JULY Scheduled

Cowal - Pre-surface dressing - preparation works

Location Duration (days) Start month Status
B836 Glen Lean 10 APR In Progress

Cowal - Surface dressing - binder and chip operations

Location Duration (days) Start month Status
B836 Glen Lean 1 JULY Scheduled

Bute and Cowal pre-surface dressing 2027/28

Location Duration (days) Start month Status
Various locations in Bute and Cowal 20 OCT Scheduled

Oban, Lorn and the Isles

Lorn - Pre-surface dressing - preparation works

Location Duration (days) Start month Status
A819 - A85 JCT  14 APR In Progress

Lorn - Surface dressing - binder and chip operations

Location Duration (days) Start month Status
A819 - A85 JCT  2 JULY Scheduled

Mull - Pre-surface dressing - preparation works

Location Duration (days) Start month Status
C46 Glenbellert / Glen Aros 4 APR In Progress

Mull - Surface dressing - binder and chip operations

Location Duration (days) Start month Status
C46 Glenbellert / Glen Aros 4 JUNE Scheduled

OLI pre-surface dressing 2027/28 

Location Duration (days) Start month Status
Various locations in OLI 20 OCT Scheduled

Helensburgh and Lomond

H&L Pre-surface dressing - preparation works

Location Duration (days) Start month Status
A814 Rhu Road Lower Glasgow - Pier Road 10 MAY Scheduled

H&L Surface dressing - binder and chip operations

Location Duration (days) Start month Status
A814 Rhu Road Lower Glasgow - Pier Road 1 JULY Scheduled

H&L Pre-surface dressing 2027/28

Location Duration (days) Start month Status
Various locations in Lomond 20 NOV Scheduled