Mid Argyll
| Location | Contractor | Treatment type | Duration - days | Start month | Status |
|---|---|---|---|---|---|
| B8024 - ORMSAY - PH 1 | Geo -Rope | Rock Armour | 60 | Feb | Complete |
| C63 - ELLARY - PH 1 | Geo -Rope | Rock Armour/ Masonry Walls | 60 | Feb | Complete |
Cowal
| Location | Contractor | Treatment type | Duration - days | Start month | Status |
|---|---|---|---|---|---|
| A815 Dunoon - Esplanade Seawall @ Argyll Ho | Geo -Rope | Reinforced concrete | 90 | Feb | In progress |
Helensburgh and Lomond
| Location | Contractor | Treatment type | Duration - days | Start month | Status |
|---|---|---|---|---|---|
| A814- Ardmay - south of Arrochar | Geo -Rope | Rock Netting | 5 | Feb | Complete |