Rothesay Harbour stabilisation works

Argyll and Bute Council will invest £1.9m in stabilisation works at Rothesay Harbour to prepare the pier to accommodate larger, more powerful vessels than the original pier was built to withstand.

Updated 27 June 2024. Next update: Friday 12 July 2024.

The current situation

Work is progressing to schedule.

Rock armour at the west corner of the pier has been fully consolidated with concrete. To do this, around 80 cubic metres of specialist, underwater concrete was carefully placed amongst the rock armour to 'glue' the rocks together to create a mass. This will prevent any slumping of the rock armour, further protecting the wall at this corner.

The team has now moved onto the other section of rock armour where it will carry out the same type of operation over the next few weeks.

Previous work

The contractor started work, on site, on 27 May as planned and compounds have been set up on the main Rothesay Harbour pier and the Albert Pier, which will receive material deliveries. Plant and equipment, including a crane and barge, have been delivered to the site.

Divers and engineers have begun working on night shift. The have carried out a number of dives to establish the situation beneath water level. This includes:

  • carrying out safety checks and rescues drills to ensure the safety of the dive team when working in the water: 
  • checking previously surveyed information and comparing that against what divers are observing beneath the water. We will then know if the bed has changed in a significant manner since the previous survey; and
  • establishing control points for use throughout the works.

Concrete works may begin soon so people may see concrete lorries on the pier at night from now on.

Background

Works at Rothesay Harbour will support the future of the pier by preparing it to accommodate larger, more powerful vessels than the original pier was built to withstand.

Argyll and Bute Council has appointed Shearwater Marine Ltd to undertake £1.9m stabilisation works at Rothesay Harbour. Maintaining ports and harbours is just one of the services our council provides that others don’t need to.

The contractor will mobilise at the harbour during the week beginning 20 May and the first dive is scheduled to take place on Monday 27 May

Shearwater Marine Ltd will carry out work overnight to minimise disruption to ferry operations and day-to-day travel for Bute residents and visitors should be mainly unaffected. 

However, to allow the contractor access to the site, the berth will not be available overnight. This will mean one of the Bute ferries will berth overnight in Gourock.

Work should take nine months to complete, and this is dependent on the weather and supply of materials. 

Stabilisation works at the harbour include:

  • Constructing a toe (retaining) wall at the base of the original wall to provide stability to the main harbour structure. This will extend 143m from the eastern edge of the harbour wall to the overnight ferry berth 
  • The toe wall will prevent any potential sliding or further loss of fine materials from the sea bed behind the original wall. 
  • Repair to the surface of the harbour where there has been visible settlement.

This new work builds on previous investment at the harbour to minimise scour, and so mitigate damage done by vessels over the years. Scour is when the seabed is dug out by vessels moving the water and creating channels against the harbour wall. We fitted a wavescreen which prevents vessels moving the water and creating scour and so protects the harbour wall. Since the wavescreen was fitted, we have seen a notable reduction of settlement on the top of the harbour wall.

For information on revised ferry timetables visit the CalMac website.

Did you find what you were looking for?

Why wasn't this information helpful

Limit to 250 characters.