Mid Argyll
| Work | Treatment type | Duration - days | Start month | Status |
|---|---|---|---|---|
| CULVERT Enlargement and Headwall improvements | Pipework | 10 | Sept | Scheduled |
| DITCH Reprofiling (including Verge clearance) | Excavation | 15 | Sept | Scheduled |
Kintyre
| Work | Treatment type | Duration - days | Start month | Status |
|---|---|---|---|---|
| CULVERT Enlargement and Headwall improvements | Pipework | 10 | Sept | Scheduled |
| DITCH Reprofiling (including Verge clearance) | Excavation | 15 | Sept | Scheduled |
Islands
| Work | Treatment type | Duration - days | Start month | Status |
|---|---|---|---|---|
| CULVERT Enlargement and Headwall improvements | Pipework | 10 | Sept | Scheduled |
| DITCH Reprofiling (including Verge clearance) | Excavation | 15 | Sept | Scheduled |
Oban and Lorn
| Work | Treatment type | Duration - days | Start month | Status |
|---|---|---|---|---|
| CULVERT Enlargement and Headwall improvements | Pipework | 12 | Sept | Scheduled |
| DITCH Reprofiling (including Verge clearance) | Excavation | 18 | Sept | Scheduled |
Mull
| Work | Treatment type | Duration - days | Start month | Status |
|---|---|---|---|---|
| CULVERT Enlargement and Headwall improvements | Pipework | 12 | Sept | Scheduled |
| DITCH Reprofiling (including Verge clearance) | Excavation | 18 | Sept | Scheduled |
Cowal
| Work | Treatment type | Duration - days | Start month | Status |
|---|---|---|---|---|
| CULVERT Enlargement and Headwall improvements | Pipework | 8 | Sept | Scheduled |
| DITCH Reprofiling (including Verge clearance) | Excavation | 12 | Sept | Scheduled |
Bute
| Work | Treatment type | Duration - days | Start month | Status |
|---|---|---|---|---|
| CULVERT Enlargement and Headwall improvements | Pipework | 3 | Sept | Scheduled |
| DITCH Reprofiling (including Verge clearance) | Excavation | 4 | Sept | Scheduled |
Helensburgh and Lomond
| Work | Treatment type | Duration - days | Start month | Status |
|---|---|---|---|---|
| CULVERT Enlargement and Headwall improvements | Pipework | 8 | Sept | Scheduled |
| DITCH Reprofiling (including Verge clearance) | Excavation | 12 | Sept | Scheduled |