Drainage programme - 2025-26

Drainage works planned for the 2025-26 period.

Mid Argyll

Mid Argyll - culvert and ditching enlargement
Work Treatment type Duration - days Start month Status
CULVERT Enlargement and Headwall improvements Pipework 10 Sept Scheduled
DITCH  Reprofiling  (including Verge clearance) Excavation 15 Sept Scheduled

Kintyre

Kintyre- culvert and ditching enlargement
Work Treatment type Duration - days Start month Status
CULVERT Enlargement and Headwall improvements Pipework 10 Sept Scheduled
DITCH  Reprofiling  (including Verge clearance) Excavation 15 Sept Scheduled

Islands

Islands - culvert and ditching enlargement
Work Treatment type Duration - days Start month Status
CULVERT Enlargement and Headwall improvements Pipework 10 Sept Scheduled
DITCH  Reprofiling  (including Verge clearance) Excavation 15 Sept Scheduled

Oban and Lorn

Oban and Lorn - culvert and ditching enlargement
Work Treatment type Duration - days Start month Status
CULVERT Enlargement and Headwall improvements Pipework 12 Sept Scheduled
DITCH  Reprofiling  (including Verge clearance) Excavation 18 Sept Scheduled

Mull

Mull - culvert and ditching enlargement
Work Treatment type Duration - days Start month Status
CULVERT Enlargement and Headwall improvements Pipework 12 Sept Scheduled
DITCH  Reprofiling  (including Verge clearance) Excavation 18 Sept Scheduled

Cowal

Cowal - culvert and ditching enlargement
Work Treatment type Duration - days Start month Status
CULVERT Enlargement and Headwall improvements Pipework 8 Sept Scheduled
DITCH  Reprofiling  (including Verge clearance) Excavation 12 Sept Scheduled

Bute

Bute - culvert and ditching enlargement
Work Treatment type Duration - days Start month Status
CULVERT Enlargement and Headwall improvements Pipework 3 Sept Scheduled
DITCH  Reprofiling  (including Verge clearance) Excavation 4 Sept Scheduled

Helensburgh and Lomond

Helensburgh and Lomond - culvert and ditching enlargement
Work Treatment type Duration - days Start month Status
CULVERT Enlargement and Headwall improvements Pipework 8 Sept Scheduled
DITCH  Reprofiling  (including Verge clearance) Excavation 12 Sept Scheduled