Iona Breakwater, Slipway and Toilet Block Works

The proposed rock breakwater will provide protection to the existing exposed landing slip thereby improving safety and reducing the risk of service disruption. Repairs to the slipway will also be completed and the existing toilet block will be demolished and rebuilt to current standards.

Update  22/06/2026

Details can be seen in the photos and notes below but progress since the last update (27/03/2026) is outlined here:

Breakwater

  • Marine operations remobilised on 25 April 2026 following prolonged poor weather. 
  • Toe trench excavation completed (26 April – 18 May). 
  • Rock armour deliveries from Glensanda Quarry resumed, with: 
    • ~5,600 tonnes of primary armour
    • ~4,000 tonnes of core material delivered in the month 
  • Geotextile installation commenced and progressing. 
  • First aid to navigation section installed at seabed / through breakwater. 
  • Total rock delivered to date: 55,267 tonnes. 
  • On programme with the aim of completing these Works before winter 2026/27.

Slipway

  • The sub-contractor is programmed to correct defects to the repair work during June / July.

Toilet Block

  • Opened to the public on 5 May 2026. 
  • Minor defects identified with close-out expected during June / July. 
  • Takeover from the Contractor is pending final defects correction and documentation submission. 
  • Finishing works to the area surrounding the toilet block will be completed following the full installation of the Breakwater.

Public Event for the Fionnphort Breakwater and overnight berthing facility

  • In accordance with Marine Directorate a Pre Application Consultation (PAC) was undertaken at Fionnphort on 21st May, and at Iona on the 22nd May. 

Licences and consents

Associated Matters

  • *Associated with the EIA is a Seagrass Mitigation and Monitoring Plan which was approved by the Marine Directorate in July 2025.
  • A specialist third party is undertaking Environmental monitoring and reporting throughout the construction period as required.

In order for the Council to address the conditions within the above licenses the Council set up regular meetings with Marine Directorate, Nature Scot and Environmental and Seagrass specialists.

 Works complete to date

  • Slipway site mobilisation and set-up
  • Slipway repairs
  • Toilet block site mobilisation and set-up
  • Toilet block demolition, construction of new block, connection to utilities, installation of Mechanical and Electrical components. Open to public May 2026.
  • Breakwater site mobilisation and set-up
  • Breakwater deliveries and placement of 1-3 tonne sized core rock, and 6-10 tonne primary rock by barge. Approximately 73% complete with total 53,200 tonnes delivered and placed. 
  • Seabed foundation and first section of Aid to Navigation mounting within the breakwater.

Works in progress

  • Toilet block minor defects correction.
  • Slipway Repairs defects correction.
  • Breakwater rock armour continuing delivery and placement.
  • Aid to Navigation foundation and mounting through breakwater.

Works required before completion

  • Completion of rock armour core placement, and continuing placement of ‘external’ primary rock armour to breakwater.
  • Construction of access steps detail for Aid to Navigation light
  • Tie in of breakwater to land levels
  • Mechanical and electrical elements of breakwater (Aid to Navigation light)
  • Dredging activity.
  • Replacement of existing handrails, bollard and ducting of existing electrical cables on the ferry slipway.
  • Make good any surfaces used during the Works / site compound occupation.
  • Site demobilisation for slipway, toilet block and breakwater elements.

Photos

 

Image
Iona Ferry terminal pre-works

Iona Ferry terminal pre-works

Image
Old toilet block demolition

Old toilet block demolition

Image
Toilet block sub walls

Toilet block sub walls construction

Image
Toilet block exterior

Toilet block exterior

Image
Single story toilet block building from front with ramp leading to main door at centre

Toilet block exterior 

 

Image
3 sinks along blue unit with hand dryer and mirror on side wall

Toilet block interior

Image
Toilet, sink, handrails and pull chords

Toilet block accessible cubicle

Image
Two urinals and two cubicles alone a wall

Toilet block internal

 

Image
Profiling existing ground to take rock armour

Profiling existing ground to take rock armour

Image
Primary rock armour placed around the navigation light foundation

Primary rock armour placed around the navigation light foundation

Image
Core rock replacement looking towards Iona from sea

Breakwater - core rock placement

Image
Breakwater – Glensanda Quarry rock loading operations

Breakwater – Glensanda Quarry rock loading operations

Image
Breakwater - primary rock delivery and placement

Breakwater - primary rock delivery and placement

 

Image
Breakwater - primary rock delivery and placement

Breakwater - primary rock delivery and placement

 

Image
Slipway repairs

Slipway repairs

 

Previous updates

See previous Iona Breakwater Works updates

Please answer the following about your experience using this website, not about the service you received from the organisation

Were you happy with your visit to our website today?

Thank you for your feedback