Craignure Ferry Terminal Project

Proposed construction programme

Proposed construction programme – indicative dates 

  • Outline business case review: April – June 2025 
  • Outline business case review response: June 2025 
  • EIA scoping; March – June 2025 
  • Surveys and EIA: April 2025- January 2026 
  • EIA review and licensing: January – May 2026  
  • Tender/procurement: October 2025 – May 2026 
  • Contract award: December 2026 
  • Construction start date: January 2027 
  • Construction: January 2027-January 2029 
  • Handover: January/February 2029 