Helensburgh Waterfront Development - updates

The Helensburgh Waterfront Development project is all about creating a vibrant and attractive waterfront for the town. We will post weekly updates here on the progress of the project.

Weekly update - week commencing 11th October 2021

Site Access Road Works (Junction to Tower Place Residents Car Park access)

Heron Bros have completed the works on the road at Tower place junction.

Week Commencing: 11/10/21 (Current Works) 

  • Lomond stone walling continuing.
  • Fire stopping works continuing.
  • Plantroom mechanical install ongoing.
  • Plastering to internal walls ongoing.
  • Kerbing and drainage channels.
  • Internal Joinery ongoing.
  • Rainscreen cladding ongoing.
  • Curtain Walling/ Glazing ongoing
  • Grading to footpaths and roads
  • External facia and soffit works ongoing.
  • Painting ongoing.
  • Electrical second fix ongoing
  • Install handrails along retaining walls
  • Steam Room being tiled
  • Integrated Plumbing System (IPS), Vanity units and lockers ongoing
  • Grid ceilings being installed. 

Week commencing: 18/10/21(Look ahead)

  • Lomond Stone walling ongoing.
  • Coping stones to retaining walls ongoing
  • Fire stopping works progressing
  • Plastering to internal walls ongoing
  • Rainscreen cladding ongoing
  • Install handrails along retaining walls 1 & 2
  • Curtain Walling/Glazing ongoing
  • Kerbing and drainage channels
  • External facia and soffit works ongoing
  • Internal joinery ongoing
  • Learner pool testing to start
  • Painting ongoing.
  • Electrical second fix ongoing
  • Grid Ceiling being installed
  • Steam room being tiled
  • IPS, Vanity units and lockers ongoing
  • Reception desk installation
  • Tiling to wet change will start
  • Sanitary ware delivered to site.

Weekly update - week commencing 4th October 2021

John Muir Way Art Study

The results from the recent survey are:.

16 responses were received, presenting a range of views on the two location options and on the creative ideas in the report. Comments were made both for and against relocating the John Muir Way start/end point roundel to the new civic space being created at the corner of Sinclair Street and West Clyde Street, and on enhancing this with additional artwork at a range of scales. Comments were also made for and against remaining at the current location on the grassy esplanade. On balance, there was no clear consensus to support relocating the John Muir Way terminus to the new civic space. 

The Green Action Trust, have  made the decision, that for the time being, the John Muir Way will remain in its current location. No additional artwork will be added here due to the risk/limitations presented by the underlying attenuation tanks. The clearest consensus was in suggestions that the end of the pier would be the optimal location for the John Muir Way, if this was restored at some point in the future.

Site Access Road Works (Junction to Tower Place Residents Car Park access)

Heron Bros have completed the works on the road at Tower place junction. Some paving will be ongoing the rest of this week.

Scottish Water Mains Water Supply

Water main is now installed, tested, backfilled and reinstated.

Week Commencing: 4/10/21 (Current Works)

  • Lomond stone walling continuing.
  • Fire stopping works progressing.
  • Plantroom mechanical install.
  • Plastering to internal walls ongoing.
  • Kerbing and drainage channels.
  • Internal Joinery ongoing.
  • Rainscreen cladding ongoing.
  • Curtain Walling/ Glazing ongoing
  • Grading to footpaths and roads
  • External facia and soffit works ongoing.
  • Painting ongoing.
  • Electrical second fix ongoing
  • Install handrails along retaining walls
  • Steam Room being tiled
  • Transferring water from the Learner pool to the balance tanks to begin final test.
  • IPS, Vanity units and lockers ongoing 

Week commencing: 11/10/21(Look ahead) 

  • Lomond Stone walling ongoing.
  • Coping stones to retaining walls ongoing
  • Fire stopping works progressing
  • Plastering to internal walls ongoing
  • Rainscreen cladding ongoing
  • Install handrails along retaining walls 1&2
  • Curtain Walling/Glazing ongoing
  • Kerbing and drainage channels
  • External facia and soffit works ongoing
  • Internal joinery ongoing
  • Learner pool testing to start
  • Painting ongoing.
  • Electrical second fix ongoing
  • Streetlight heads being installed.
  • Grid Ceiling being installed
  • Steam room being tiled
  • IPS, Vanity units and lockers ongoing
  • Reception desk installation

Weekly update - week commencing 20th September 2021

John Muir Way Art Study

In early 2021, the Green Action Trust secured funding from Scotland Loves Local to commission art organisation WAVEparticle to consult with the community in Helensburgh in developing a brief for a new/enhanced artwork to mark the start/end of the John Muir Way. A series of online consultation workshops took place in April and May 2021.

Plans to relocate the existing John Muir Way ‘footprints’ artwork, as part of the Helensburgh Waterfront Development project, had been developed in response to feedback from visitors that the current route terminus was difficult to find. The opportunity to relocate the terminus and existing artwork, to become the centrepiece of the new civic space being created at the corner of Sinclair Street and West Clyde Street, was welcomed by the Green Action Trust to provide greater visibility and profile for the route within the town.

The John Muir Way Artwork Study set out to explore how the existing artwork, once relocated, could be enhanced to offer even greater visibility and relevance. The cost for relocating the existing artwork (but not enhancing) is included in the Waterfront Development project.

The final report documents the process followed, ideas captured, alternative locations explored and recommendations going forward.

The report can be downloaded here: https://johnmuirway.org/news/show/john-muir-way-helensburgh-artwork-study

The webpage also includes a survey monkey link for those who’d like to provide feedback on the report and its recommendations. Please note that the deadline to comment is midnight on Sunday 26th September. This date is set to reflect the potential to apply to Scotland Loves Local for next stage funding; the application deadline is 1 October.

Week Commencing: 20/09/21 (Current Works)

  • Lomond stone walling continuing.
  • Fire stopping works progressing.
  • Plantroom mechanical install.
  • Plastering to internal walls ongoing.
  • Kerbing and drainage channels.
  • Internal Joinery ongoing.
  • Rainscreen cladding ongoing.
  • Curtain Walling/ Glazing ongoing
  • Grading to footpaths and roads
  • External facia and soffit works ongoing.
  • Main pool pre tile test
  • Painting ongoing.
  • Electrical second fix ongoing
  • Install handrails along retaining walls
  • Steam Room being installed
  • Transferring water from the Main Pool into the learner pool

Week commencing: 27/09/21(Look ahead)

  • Lomond Stone walling ongoing.
  • Coping stones to retaining walls ongoing
  • Fire stopping works progressing
  • Plastering to internal walls ongoing
  • Rainscreen cladding ongoing
  • Install handrails along retaining walls 1&2
  • Curtain Walling/Glazing ongoing
  • Kerbing and drainage channels
  • External facia and soffit works ongoing
  • Internal joinery ongoing
  • Learner pool testing to start
  • Painting ongoing.
  • Electrical second fix ongoing
  • Streetlight heads being installed.
  • Grid Ceiling being installed
  • Steam room being installed
  • Filter Vessels being installed

Weekly update - week commencing 13th September 2021

Site Access Road Works (Junction to Tower Place Residents Car Park access)
Heron Bros have commenced kerbing and Resurfacing works 7th September to the Helensburgh Waterfront Development Access Road (Sinclair Street) between the traffic junction and Site Entrance/Tower Place Residents Carpark. These works were originally programmed in Phase 2 (September 2022) once the New Leisure Centre, Car Park and Public Realm  (Phase 1) works were completed and opened in August 2022. However as Granite Kerbs and Granite Pavers purchased several years ago by the Council from the CHORD Contractor are being utilised as much as possible within the Public Realm areas of the project. This opened up the opportunity to bring forward these works by 12 months, undertaking the works now would be less intrusive and disruptive to the Town, than the later original programed date when the Leisure Centre and Phase 1 are fully open to the public.

  1. 20/09/21 Road Planer and Tarmac squad arrives. We will need to keep access to site and Tower Place Residents Car Park through the course of these works so will need to manage the traffic to allow the works to be undertaken.
  2. 22/09/21 Lay  tarmac base course of tar to the road outside site. Access will be disrupted but we will do our utmost to maintain access throughout.
  3. 23/09/21 Lay tarmac binder course to roads, same disruption as above.
  4. 24/09/21 complete base and binder. Tarmac top course will be completed at a later date, but we will ensure any difference in levels will be ramped well upon completion until top course is ready to be complete.

Week Commencing: 13/09/21 (Current Works)

  • Lomond stone walling continuing.
  • Fire stopping works progressing.
  • Plantroom mechanical install.
  • Plastering to internal walls ongoing.
  • Kerbing and drainage channels.
  • Internal Joinery ongoing.
  • Rainscreen cladding ongoing.
  • Curtain Walling/ Glazing ongoing
  • Grading to footpaths and roads
  • External facia and soffit works ongoing.
  • Main pool pre tile test
  • Painting ongoing.
  • Poolside lights being installed
  • Distribution boards complete and ready for power
  • Electrical second fix ongoing
  • Install handrails along retaining walls 1&2
  • Raised Access Flooring installation complete

Week commencing: 20/09/21(Look ahead)

  • Lomond Stone walling ongoing.
  • Coping stones to retaining walls ongoing
  • Fire stopping works progressing
  • Plastering to internal walls ongoing
  • Rainscreen cladding ongoing
  • Install handrails along retaining walls 1&2
  • Curtain Walling/Glazing ongoing
  • Kerbing and drainage channels
  • External facia and soffit works ongoing
  • Internal joinery ongoing
  • Learner pool testing to start
  • Painting ongoing.
  • Electrical second fix ongoing
  • Streetlight heads being installed.

Weekly update - week commencing 6th September 2021

Week Commencing: 6/09/21 (Current Works)

  • Lomond stone walling continuing.
  • Fire stopping works progressing.
  • Plantroom mechanical install.
  • Plastering to internal walls ongoing.
  • Kerbing and drainage channels.
  • Internal Joinery ongoing.
  • Rainscreen cladding ongoing.
  • Curtain Walling/ Glazing ongoing
  • Grading to footpaths and roads
  • External facia and soffit works ongoing.
  • Filling of the main pool for pre tiling test.
  • Painting ongoing.
  • Poolside lights being installed
  • Installation of Integrated Plumbing System (IPS) complete
  • Distribution boards complete and ready for power
  • Electrical second fix ongoing
  • Install handrails along retaining walls 1&2
  • Raised Access Flooring installation progressing

Week commencing: 13/09/21(Look ahead)

  • Lomond Stone walling ongoing.
  • Coping stones to retaining walls ongoing
  • Fire stopping works progressing
  • Plastering to internal walls ongoing
  • Rainscreen cladding ongoing
  • Install handrails along retaining walls 1&2
  • Curtain Walling/Glazing ongoing
  • Kerbing and drainage channels
  • External facia and soffit works ongoing
  • Internal joinery ongoing
  • Main pool testing to begin.
  • Painting ongoing.
  • Electrical second fix ongoing
  • Streetlight heads being installed.
  • Raised Access Flooring progressing

Weekly update - week commencing 30th August 2021

On Tuesday 31st August, 2021 we celebrated the 1st Anniversary of Heron Bros Ltd starting on-site. With ongoing Covid restrictions, it has taken a huge team effort from the Council, Heron Bros Ltd and our Internal and External design consultants to get us to this important milestone.

It is remarkable to think of the progress to date considering the back office staff behind the Waterfront Development are working remotely to deliver the project.

The progress achieved in the face of considerable challenge is a testament to the power of partnership and professionalism. Congratulations to everyone involved.

Week Commencing: 30/08/21 (Current Works)

  • Lomond stone walling continuing.
  • M&E progressing.
  • Fire stopping works progressing.
  • Plantroom mechanical install.
  • Plastering to internal walls ongoing.
  • Kerbing and drainage channels.
  • Internal Joinery ongoing.
  • Rainscreen cladding ongoing.
  • Curtain Walling/ Glazing ongoing
  • Grading to footpaths and roads
  • External facia and soffit works ongoing.
  • Filling of the main pool for pre tiling test.
  • Painting ongoing.
  • Poolside lights being installed
  • Installation of Integrated Plumbing System (IPS) panels starts.
  • DB boards complete and ready for power
  • Electrical second fix ongoing
  • Install handrails along retaining walls 1&2

Week commencing: 06/09/21(Look ahead)

  • Lomond Stone walling ongoing.
  • Coping stones to retaining walls ongoing
  • Fire stopping works progressing
  • M&E Progressing.
  • Plastering to internal walls ongoing
  • Rainscreen cladding
  • Install handrails along retaining walls 1&2
  • Curtain Walling/Glazing ongoing
  • Kerbing and drainage channels
  • External facia and soffit works ongoing
  • Internal joinery ongoing
  • Filling of the main pool for pre tiling test.
  • Painting ongoing.
  • Installation of Integrated Plumbing System (IPS) panels complete
  • Electrical second fix ongoing

Weekly update - week commencing 23rd August 2021

Mains Gas Supply
Scottish Gas Networks (SGN) have now completed installation of the new gas connection.

Week Commencing: 23/08/21 (Current Works)

  • Lomond stone walling continuing.
  • M&E progressing.
  • Fire stopping works progressing.
  • Plantroom mechanical install.
  • Plastering to internal walls ongoing.
  • Kerbing and drainage channels.
  • Internal Joinery ongoing.
  • Rainscreen cladding ongoing.
  • Curtain Walling/ Glazing ongoing
  • Grading to footpaths and roads
  • External facia and soffit works ongoing.
  • Filling of the main pool for pre tiling test.
  • Painting ongoing.
  • SGN Gas Connection works completed

Week commencing: 30/08/21(Look ahead)

  • Lomond Stone walling ongoing.
  • Coping stones to retaining walls ongoing
  • Fire stopping works progressing
  • M&E Progressing.
  • Plastering to internal walls ongoing
  • Rainscreen cladding
  • Install handrails along retaining walls 1&2
  • Curtain Walling/Glazing ongoing
  • Kerbing and drainage channels
  • External facia and soffit works ongoing
  • Internal joinery ongoing
  • Filling of the main pool for pre tiling test.
  • Painting ongoing.
  • Installation of Integrated Plumbing System (IPS) panels starts.

Weekly update - week commencing 16th August 2021

Considerate Constructors Scheme (CCS)
The project has once again achieved a rating of excellent in a recent audit conducted by the Considerate Constructors Scheme (CCS), a not-for-profit, independent organisation founded to raise standards in the construction industry. Construction sites, companies and suppliers voluntarily register with the scheme and agree to abide by the code of considerate practice, designed to encourage best practice beyond statutory requirements. https://www.ccscheme.org.uk/

Heron Bros where commended in this recent CCS audit for extensive COVID-19 protection measures with the introduction of biometric scanner that all employees use for clocking in and out every day. The scanner uses retina recognition and also scans temperature giving a green light to proceed or a red light to leave site. It is linked back to an online system allowing us to monitor or review when necessary.

Mains Gas Supply
Scottish Gas Networks (SGN) commenced laying a new gas main connection to supply the new leisure building Monday 9th August 2021. This mains gas connection will commence at the entrance to the pier run part way down the left hand side of the pier before entering the Heron Bros site at the new public realm ramp behind the site hoardings. Pedestrian access to the Public Toilets and to the pier will maintained during these works which are programmed to last up to 3 weeks.

Week Commencing: 16/08/21 (Current Works)

  • Lomond stone walling continuing.
  • Lomond stone to both the bin store and the substation.
  • M&E progressing.
  • Fire stopping works progressing
  • Plantroom mechanical install
  • Plastering to internal walls ongoing
  • Kerbing and drainage channels
  • Internal Joinery ongoing
  • Rainscreen cladding ongoing
  • Curtain Walling/ Glazing ongoing
  • Grading to footpaths and roads
  • External facia and soffit works ongoing.
  • SGN Works ongoing
  • Filling of the main pool for pre tiling test.

Week commencing: 23/08/21(Look ahead)

  • Lomond Stone walling ongoing.
  • Coping to retaining walls ongoing
  • Lomond stone to both the bin store and the substation.
  • Fire stopping works progressing
  • M&E Progressing.
  • Plastering to internal walls ongoing
  • Rainscreen cladding
  • Install handrails along retaining walls 1&2
  • Curtain Walling/Glazing ongoing
  • SGN works ongoing.
  • Kerbing and drainage channels
  • External facia and soffit works ongoing
  • Internal joinery ongoing
  • Plantroom/Escape stairs painting

Weekly update - week commencing 9th August 2021

Scottish Water Mains Water Supply
Water main is now installed, tested, backfilled and reinstated with exception of the fire hydrant, adjacent to Public Toilets which will be completed shortly.

Mains Gas Supply
Scottish Gas Networks (SGN) will commence laying a new gas main connection to supply the new leisure building w/c 9th August, 2020. This mains gas connection will commence at the entrance to the pier run part way down the left hand side of the pier before entering the Heron Bros site at the new public realm ramp behind the site hoardings. Pedestrian access to the Public Toilets and to the pier will maintained during these works which are programmed to last up to 3 weeks.

Week Commencing: 9/08/21 (Current Works)

  • Lomond stone walling continuing.
  • Lomond stone to both the bin store and the substation.
  • M&E progressing.
  • Fire stopping works progressing
  • Plantroom mechanical install
  • Plastering to internal walls ongoing
  • Kerbing and drainage channels
  • Internal Joinery ongoing
  • Rainscreen cladding ongoing
  • Curtain Walling/ Glazing ongoing
  • Street lighting installation ongoing
  • Grading to footpaths and roads
  • Water main complete and backfilled.
  • External facia and soffit works ongoing.
  • SGN Works commence

Week commencing: 16/08/21(Look ahead)

  • Lomond Stone walling ongoing.
  • Coping to retaining walls ongoing
  • Lomond stone to both the bin store and the substation.
  • Fire stopping works progressing
  • M&E Progressing.
  • Plastering to internal walls ongoing
  • Rainscreen cladding
  • Install handrails along retaining walls 1&2
  • Curtain Walling/Glazing ongoing
  • SGN works ongoing.
  • Kerbing and drainage channels
  • External facia and soffit works ongoing
  • Internal joinery ongoing
  • Start filling pool for pre tiling testing.

Weekly update - week commencing 2nd August 2021

Scottish Water Mains Water Supply
Scottish Water commenced laying a new water main connection to supply the new leisure building w/c 12 July 2021. Water main is now installed, tested, backfilled and reinstated with exception of the fire hydrant, adjacent to Public Toilets which will be completed shortly.

Week Commencing: 2/08/21 (Current Works)

  • Lomond stone walling continuing.
  • Lomond stone to both the bin store and the substation.
  • M&E first fix progressing.
  • Fire stopping works progressing
  • Plantroom mechanical install
  • Plastering to internal walls ongoing
  • Kerbing and drainage channels
  • Internal Joinery ongoing
  • Rainscreen cladding insulation
  • Curtain Walling ongoing
  • Street lighting installation ongoing
  • Grading to footpaths and roads
  • Water main complete and backfilled.

Week commencing: 9/08/21(Look ahead)

  • Lomond Stone walling ongoing.
  • Coping to retaining walls ongoing
  • Lomond stone to both the bin store and the substation.
  • Fire stopping works progressing
  • M&E first fix Progressing.
  • Plastering to internal walls ongoing
  • Rainscreen cladding framing
  • Install handrails along retaining walls 1&2
  • Perimeter Curtain Walling
  • SGN works
  • Kerbing and drainage channels

Weekly update - week commencing 26th July 2021

Heron Bros. newsletter - summer 2021

Scottish Water Mains Water Supply
Scottish Water commenced laying a new water main connection to supply the new leisure building w/c 12 July 2021. This mains water connection will commence at the entrance to the pier run part way down the left hand side of the pier before entering the Heron Bros site at the new public realm ramp behind the site hoardings. Pedestrian access to the Public Toilets and to the pier will maintained during these works which are programmed to last up to 3 weeks, pipe work on the pier side has been completed and reinstated.

Mains Gas Supply
Scottish Gas Networks will commence laying a new gas main connection to supply the new leisure building w/c 9th August, 2020. This mains gas connection will also commence at the entrance to the pier run part way down the left hand side of the pier before entering the Heron Bros site at the new public realm ramp behind the site hoardings. Pedestrian access to the Public Toilets and to the pier will maintained during these works which are programmed to last up to 3 weeks.

Café
The newly created café area within the new Leisure Building will be run by the Council following its investment in catering and will be run in conjunction with the existing Helensburgh & Lomond Civic Centre Café’. The new café’ will offer customers the chance to relax and enjoy a coffee and food after their studio, gym or swimming session or when children are participating in activities, like swimming lessons without leaving the new Leisure Building.

Week Commencing: 26/07/21 (Current Works)

  • Lomond stone walling continuing.
  • Lomond stone to both the bin store and the substation.
  • M&E first fix progressing.
  • Fire stopping works progressing
  • Plantroom mechanical install
  • Plastering to internal walls ongoing
  • Floor screeding complete
  • Internal Joinery ongoing
  • Rainscreen cladding insulation
  • Curtain Walling ongoing
  • Street lighting installation ongoing
  • Grading to footpaths and roads
  • Water main complete and backfilled.

Week commencing: 2/08/21(Look ahead)

  • Lomond Stone walling ongoing.
  • Coping to retaining walls ongoing
  • Lomond stone to both the bin store and the substation.
  • Fire stopping works progressing
  • M&E first fix Progressing.
  • Plastering to internal walls ongoing
  • Rainscreen cladding framing
  • Install handrails along retaining walls 1&2
  • Perimeter Curtain Walling
  • Internal Curtain walling
  • Water main backfill and reinstate
  • Installation of incoming electrical ducting
  • Kerbing and drainage channels

Weekly update - week commencing 19th July 2021

Scottish Water Mains Water Supply
Scottish Water commenced laying a new water main connection to supply the new leisure building w/c 12 July 2021. This mains water connection will commence at the entrance to the pier run part way down the left hand side of the pier before entering the Heron Bros site at the new public realm ramp behind the site hoardings. Pedestrian access to the Public Toilets and to the pier will maintained during these works which are programmed to last up to 3 weeks, pipe work on the pier side has been completed, sanded and taped, once fully tested this can be back filled and reinstated.

Week Commencing: 19/07/21 (Current Works)

  • Lomond stone walling continuing.
  • M&E first fix progressing.
  • Intumescent painting complete
  • Plantroom mechanical install
  • Plastering to internal walls ongoing
  • Complete floor screeding
  • Internal Joinery ongoing
  • Rainscreen cladding insulation
  • Curtain Walling ongoing
  • Street lighting installation ongoing
  • Grading to footpaths and roads
  • Water main dig ongoing

Week commencing: 26/07/21(Look ahead)

  • Lomond Stone walling ongoing.
  • Coping to retaining walls ongoing
  • M&E first fix Progressing.
  • Plastering to internal walls ongoing
  • Rainscreen cladding framing
  • Standing streetlights
  • Perimeter Curtain Walling
  • Internal Curtain walling
  • Installation of water mains
  • Installation of incoming electrical ducting
  • Kerbing and drainage channels

Weekly update - week commencing 12th July 2021

Scottish Water Mains Water Supply
Scottish Water have yesterday 12 July, 2021 commenced laying a new water main connection to supply the new leisure building. This mains water connection will commence at the entrance to the pier run part way down the left hand side of the pier before entering the Heron Bros site at the new public realm ramp behind the site hoardings. Pedestrian access to the Public Toilets and to the pier will maintained during these works which are programmed to last up to 3 weeks, however it is anticipated that full access to the pier can be reinstated w/c 19 July, 2021.

Mains Gas Supply
Scottish Gas Networks will commence laying a new gas main connection to supply the new leisure building w/c 9th August, 2020. This mains gas connection will also commence at the entrance to the pier run part way down the left hand side of the pier before entering the Heron Bros site at the new public realm ramp behind the site hoardings. Pedestrian access to the Public Toilets and to the pier will maintained during these works which are programmed to last up to 3 weeks.

Week Commencing: 12/07/21 (Current Works)

  • Lomond stone walling continuing.
  • M&E first fix progressing.
  • Intumescent painting complete
  • Plantroom mechanical install
  • Plastering to internal walls ongoing
  • Floor screeding ongoing
  • Internal Joinery ongoing
  • Rainscreen cladding insulation
  • Curtain Walling ongoing
  • Street lighting installation ongoing
  • Grading to footpaths and roads
  • Water main dig ongoing

Week commencing: 19/07/21(Look ahead)

  • Lomond Stone walling ongoing.
  • M&E first fix Progressing.
  • Plastering to internal walls ongoing
  • Floor Screeding ongoing
  • Rainscreen cladding framing
  • Standing streetlights
  • Perimeter Curtain Walling
  • Internal Curtain walling
  • Installation of water mains
  • Installation of incoming electrical ducting
  • Kerbing and drainage channels

Weekly update - week commencing 5th July 2021

Scottish Water Mains Water Supply
Scottish Water will commence laying a new water main connection to supply the new leisure building w/c 12 July, 2021. This mains water connection will commence at the entrance to the pier run part way down the left hand side of the pier before entering the Heron Bros site at the new public realm ramp behind the site hoardings. Pedestrian access to the Public Toilets and to the pier will maintained during these works which are programmed to last up to 3 weeks.

Mains Gas Supply
Scottish Gas Networks will commence laying a new gas main connection to supply the new leisure building w/c 2 August, 2020. This mains gas connection will also commence at the entrance to the pier run part way down the left hand side of the pier before entering the Heron Bros site at the new public realm ramp behind the site hoardings. Pedestrian access to the Public Toilets and to the pier will maintained during these works which are programmed to last up to 3 weeks.

Café
The newly created café area within the new Leisure Building will be run by the Council following its investment in catering and will be run in conjunction with the existing Helensburgh & Lomond Civic Centre Café’.

Week Commencing: 5/07/21 (Current Works)

  • Lomond stone walling continuing.
  • M&E first fix progressing.
  • Intumescent painting ongoing.
  • Tar to footpaths ongoing
  • Plantroom mechanical install
  • Plastering to internal walls ongoing
  • Floor screeding ongoing
  • Internal Joinery ongoing
  • Rainscreen cladding insulation
  • Curtain Walling
  • Street lighting installation
  • Grading to footpaths and roads

Week commencing: 12/07/21(Look ahead)

  • Lomond Stone walling ongoing.
  • M&E first fix Progressing.
  • Intumescent painting ongoing.
  • Plastering to internal walls ongoing
  • Floor Screeding ongoing
  • Rainscreen cladding framing
  • Standing streetlights
  • Perimeter Curtain Walling
  • Internal Curtain walling
  • Installation of water mains
  • Installation of incoming electrical ducting
  • Kerbing and drainage channels

Weekly update - week commencing 14th June 2021 (covering up to 4th July 2021)

Week commencing: 14/06/21 (Current Works)

  • Lomond stone walling continuing.
  • M&E first fix progressing.
  • Intumescent painting ongoing.
  • Roof install ongoing. (Welding of seams and penetrations)
  • Kerbing to Carpark ongoing
  • Drainage channels to the carpark perimeter.
  • Installation of internal floor gullies.
  • Plastering to internal walls ongoing
  • Floor screeding ongoing
  • Lift install ongoing
  • Rainscreen cladding insulation
  • Curtain Walling

Week commencing: 21/06/21(Look ahead)

  • Lomond Stone walling ongoing.
  • M&E first fix Progressing.
  • Intumescent painting ongoing.
  • Kerb and Channel install.
  • Plastering to internal walls ongoing
  • Floor Screeding ongoing
  • Lift installation ongoing
  • Tarmac surfacing to car parking bays
  • Rainscreen cladding framing
  • Standing streetlights
  • Perimeter Curtain Walling
  • Internal Curtain walling
  • Installation of incoming electrical ducting

Week commencing: 28/06/21(Look ahead)

  • Lomond Stone walling ongoing.
  • Installation of street light and CCTV ducting ongoing.
  • M&E first fix Progressing.
  • Kerb and Channel install.
  • Plastering to internal walls ongoing
  • Floor Screeding ongoing
  • Tarmac surfacing to roads and paths
  • Rainscreen cladding tiles being installed
  • Curtain Walling
  • Installation of incoming electrical cables

Weekly update - week commencing 7th June 2021

Week Commencing: 7/06/21 (Current Works)

  • Lomond stone walling continuing.
  • M&E first fix progressing.
  • Intumescent painting ongoing.
  • Roof install ongoing. (Welding of seams and penetrations)
  • Blockwork to substation walls ongoing
  • Kerbing to Carpark ongoing
  • Drainage channels to the carpark perimeter.
  • Installation of internal floor gullies.
  • Plastering to internal walls ongoing
  • Floor screeding ongoing
  • Lift install ongoing
  • Rainscreen cladding insulation
  • Curtain Walling

Week commencing: 14/06/21(Look ahead)

  • Lomond Stone walling ongoing.
  • Installation of street light and CCTV ducting ongoing.
  • M&E first fix Progressing.
  • Intumescent painting ongoing.
  • Installation of internal gulley’s.
  • Kerb and Channel install.
  • Plastering to internal walls ongoing
  • Floor Screeding ongoing
  • Lift installation ongoing
  • Tarmac surfacing to car parking bays
  • Rainscreen cladding insulation
  • Standing streetlights
  • Curtain Walling

Update - 4th June 2021 - temporary footpath closure

Heron Bros will be commencing electrical enabling works w/c 7th June, which will require the temporary closure of the footpath on the Southern Side of West Clyde Street between the junction of Sinclair Street and Colquhoun Street. Vehicle and Pedestrian access to the pier, public toilets swimming pool and car park will be maintained during these works.

Following Heron Bros electrical enabling works, the footpath will remain temporary closed to facilitate cable laying by Energetics and final electrical  connection by Scottish Power for a period of approximately 12+ weeks.

Helensburgh Waterfront - temporary footpath closure - location map

Weekly update - week commencing 31st May 2021

Week Commencing: 31/05/21 (Current Works)

  • Lomond stone walling continuing.
  • M&E first fix progressing.
  • Intumescent painting ongoing.
  • Roof install ongoing. (Welding of seams and penetrations)
  • Blockwork to substation walls ongoing
  • Kerbing to Carpark ongoing
  • Drainage channels to the carpark perimeter.
  • Installation of internal floor gullies.
  • Plastering to internal walls ongoing
  • Floor screeding ongoing
  • Lift install ongoing
  • Rainscreen cladding insulation

Week commencing: 7/06/21(Look ahead)

  • Lomond Stone walling ongoing.
  • Installation of street light and CCTV ducting ongoing.
  • Blockwork to substation walls ongoing
  • M&E first fix Progressing.
  • Intumescent painting ongoing.
  • Installation of internal gulley’s.
  • Kerb and Channel install.
  • Plastering to internal walls ongoing
  • Floor Screeding ongoing
  • Lift installation ongoing
  • Tarmac surfacing to car parking bays
  • Rainscreen cladding insulation
  • Standing streetlights

Weekly update - week commencing 24th May 2021

The Helensburgh Waterfront Development celebrated a major construction milestone with a traditional ‘ topping out’ ceremony last Friday (21st) marking the completion of the buildings structure and roof - read more about the ceremony in our press release

Week Commencing: 24/05/21 (Current Works)

  • Lomond stone walling continuing.
  • M&E first fix progressing.
  • Intumescent painting ongoing.
  • Roof install ongoing.
  • Blockwork to substation walls ongoing
  • Kerbing to Carpark ongoing
  • Drainage channels to the carpark perimeter.
  • Installation of internal floor gullies.
  • Plastering to internal walls ongoing
  • Floor screeding ongoing
  • Lift install ongoing
  • Concrete to east slipway

Week commencing: 31/05/21(Look ahead)

  • Lomond Stone walling ongoing.
  • Installation of street light and CCTV ducting ongoing.
  • Blockwork to substation walls ongoing
  • M&E first fix Progressing.
  • Intumescent painting ongoing.
  • Installation of internal gulley’s.
  • Kerb and Channel install.
  • Plastering to internal walls ongoing
  • Floor Screeding ongoing
  • Lift installation ongoing
  • Tarmac surfacing to car parking bays

Weekly update - week commencing 17th May 2021

Week Commencing: 17/05/21 (Current Works)

  • Blockwork to internal walls continues.
  • Lomond stone walling continuing.
  • External Drainage ongoing.
  • Installation of Street light and CCTV ducting ongoing.
  • M&E first fix progressing.
  • Intumescent painting ongoing.
  • Roof install ongoing.
  • Blockwork to substation walls ongoing
  • Kerbing to Carpark ongoing
  • Drainage channels to the carpark perimeter.
  • Installation of internal floor gullies.
  • Plastering to internal walls ongoing
  • Underfloor heating ongoing
  • Floor screeding ongoing
  • Lift install has started.

Week commencing: 24/05/21(Look ahead)

  • Lomond Stone walling ongoing.
  • External Drainage ongoing.
  • Installation of street light and CCTV ducting ongoing.
  • Blockwork Internal walls to Ground Floor Pool Hall.
  • Blockwork to substation walls ongoing
  • M&E first fix Progressing.
  • Intumescent painting ongoing.
  • Roof installation ongoing.
  • Installation of internal gulley’s.
  • Kerb and Channel install.
  • Plastering to internal walls ongoing
  • Underfloor heating ongoing
  • Floor Screeding ongoing
  • Lift installation ongoing

Weekly update - week commencing 10th May 2021

Week Commencing: 10/05/21 (Current Works)

  • Blockwork to internal walls continues.
  • Lomond stone walling continuing.
  • External Drainage ongoing.
  • Installation of Street light and CCTV ducting ongoing.
  • M&E first fix progressing.
  • Intumescent painting ongoing.
  • Roof Insulation install ongoing.
  • Blockwork to substation walls ongoing
  • Kerbing to Carpark ongoing
  • Drainage channels to the carpark perimeter.
  • Installation of internal floor gullies.
  • Plastering to internal walls ongoing
  • Underfloor heating ongoing
  • Floor screeding starts this week

Week commencing: 17/05/21(Look ahead)

  • Lomond Stone walling ongoing.
  • External Drainage ongoing.
  • Installation of street light and CCTV ducting ongoing.
  • Blockwork Internal walls to Ground Floor Pool Hall.
  • Blockwork to substation walls ongoing
  • M&E first fix Progressing.
  • Intumescent painting ongoing.
  • Roof installation ongoing.
  • Steel work to bin store.
  • Installation of internal gulley’s.
  • Kerb and Channel install.
  • Plastering to internal walls ongoing
  • Underfloor heating ongoing
  • Floor Screeding ongoing
  • Lift installation

Weekly update - week commencing 3rd May 2021

Week Commencing: 03/05/21 (Current Works)

  • Blockwork to internal walls continues.
  • Lomond stone walling continuing.
  • External Drainage ongoing.
  • Installation of Street light and CCTV ducting ongoing.
  • M&E first fix progressing.
  • Intumescent painting ongoing.
  • Roof Insulation install ongoing.
  • Blockwork to substation walls ongoing
  • Casting concrete for the emerging steps by the pier and slipway Complete
  • Kerbing to Carpark begins.
  • Drainage channels to the carpark perimeter.
  • Installation of internal floor gullies.
  • Plastering to internal walls starts this week
  • Underfloor heating starts this week

Week commencing: 10/05/21(Look ahead)

  • Lomond Stone walling ongoing.
  • External Drainage ongoing.
  • Installation of street light and CCTV ducting ongoing.
  • Blockwork Internal walls to Ground Floor Pool Hall.
  • M&E first fix Progressing.
  • Intumescent painting ongoing.
  • Roof installation ongoing.
  • Steel work to bin store.
  • Installation of internal gulley’s.
  • Casting concrete for the emerging steps by the pier and slipway.
  • East slipway continue.
  • Kerb and Channel install.
  • Plastering to internal walls ongoing
  • Underfloor heating ongoing

Weekly update - week commencing 26th April 2021

Week Commencing: 26/04/21 (Current Works)

  • Blockwork to internal walls continues.
  • Lomond stone walling continuing.
  • External Drainage ongoing.
  • Installation of Street light and CCTV ducting ongoing.
  • M&E first fix progressing.
  • Intumescent painting ongoing.
  • Roof Insulation install ongoing.
  • Netting removed.
  • Blockwork to substation walls.
  • Casting concrete for the emerging steps by the pier and slipway.
  • East slipway works start.
  • East Slipway Floodgate Installation.
  • Kerbing to Carpark begins.
  • Drainage channels to the carpark perimeter.
  • Installation of internal floor gullies.

Week commencing: 03/05/21(Look ahead)

  • Lomond Stone walling ongoing.
  • External Drainage ongoing.
  • Installation of street light and CCTV ducting ongoing.
  • Blockwork Internal walls to Ground Floor Pool Hall.
  • M&E first fix Progressing.
  • Intumescent painting ongoing.
  • Roof installation ongoing.
  • Steel work to bin store.
  • Installation of internal gulley’s.
  • Casting concrete for the emerging steps by the pier and slipway.
  • East slipway continue.
  • Kerb and Channel install.
  • Casting concrete to east slipway.
  • Start underfloor heating.