MR AND MRS JOHN AND JULIE MCNAMEE: ALTERATIONS/EXTENSION AND CHANGE OF USE OF ECCLESIASTICAL BUILDING (CLASS 10) TO FORM DWELLINGHOUSE (CLASS 9), INSTALLATION OF SEWAGE TREATMENT PLANT AND FORMATION OF VEHICULAR ACCESS (REVISED APPLICATION TO CREATE

Meeting: 18/11/2020 - Planning, Protective Services and Licensing Committee (Item 5)

5 MR AND MRS JOHN AND JULIE MCNAMEE: ALTERATIONS/EXTENSION AND CHANGE OF USE OF ECCLESIASTICAL BUILDING (CLASS 10) TO FORM DWELLINGHOUSE (CLASS 9), INSTALLATION OF SEWAGE TREATMENT PLANT AND FORMATION OF VEHICULAR ACCESS (REVISED APPLICATION TO CREATE DOMESTIC CURTILAGE): INVERCHAOLAIN CHURCH, TOWARD (REF: 19/00849/PP) pdf icon PDF 207 KB

Report by Head of Development and Economic Growth

:

Additional documents:

Minutes:

The Planning Officer spoke to the terms of the report and to supplementary report number 1.  The application site lies within the Countryside Zone where policy LDP DM 1 will only support proposals that are infill, redevelopment, rounding off or change of use.  In this case the conversion of the church building and partial use of the adjacent field for associated domestic purposes is considered to be consistent with the settlement and spatial strategy.    The Council own the graveyard which completely surrounds the church.  The proposed external alterations to convert the church into a mainstream dwellinghouse are considered to be minimal and the physical appearance and character of the church would be relatively untouched.  The proposal has attracted a total of 19 letters of objection, including 5 late representations detailed in the supplementary report.  The concerns raised relate to the use of the church building as a dwellinghouse, impact on existing amenity and privacy as a historic and functional graveyard, access and car parking issues and serving issues.   There have been no objections from consultees subject to conditions.  It is not considered that holding a discretionary hearing would add value to the planning process.  The proposal is considered to be consistent with the relevant development plan policies and it was recommended that planning permission be granted subject to the conditions and reasons detailed in the report of handling.

 

Decision

 

The Committee agreed to grant planning permission subject to the following conditions and reasons:

 

1.    The development shall be implemented in accordance with the details specified on the application form dated 25th April 2019 and the approved drawings listed in the table below, and supporting information, unless the prior written approval of the planning authority is obtained for an amendment to the approved details under Section 64 of the Town and Country Planning (Scotland) Act 1997.

 

Plan Title.

 

Plan Ref. No.

Version

Date Received

1:10,000 Supplementary  Location Plan

1 of 14 Drawing no. 1365-02-14E  

RevE

04/08/2020

1:1250 Location Plan   

2 of 14 Drawing no. 1365-02-01F 

RevF

04/08/2020

1:500 Site Plan as Existing   

3 of 14 Drawing no. 1365-02-02G

RevG

04/08/2020

1:100 Ground Floor Plan as Existing

4 of 14 Drawing no. 1365-02-04A

RevA

26/04/2019

1:100 First Floor Plan as Existing    

5 of 14 Drawing no. 1365-02-05A

RevA

26/04/2019

1:100 Elevations as Existing    

6 of 14 Drawing no. 1365-02-06A

RevA

26/04/2019

1:100 Sections as Existing   

7 of 14 Drawing no. 1365-02-07

 

26/04/2019

nts 3D Views as Existing

8 of 14 Drawing no. 1365-02-08

 

26/04/2019

1:500 Site Plan as Proposed   

9 of 14 Drawing no. 1365-02-03G

RevG

04/08/2020

1:100 Ground Floor Plan as Proposed

10 of 14 Drawing no. 1365-02-09A

RevA

26/04/2019

1:100 First Floor Plan as Proposed     

11 of 14 Drawing no. 1365-02-10A

RevA

26/04/2019

1:100 Elevations as Proposed    

12 of 14 Drawing no. 1365-02-11B

RevB

26/04/2019

1:100 Sections as Proposed     

13 of 14 Drawing no. 1365-02-12

 

26/04/2019

nts 3D Views as Proposed

14 of 14 Drawing no. 1365-02-13

 

26/04/2019

 

Reason: For the purpose of clarity, to ensure that the development is implemented in accordance with the approved details.

 

2.    Prior to the commencement of any development, the existing private water supply and infrastructure for storage and distribution will need to meet the requirements of The Water Intended for Human Consumption (Private Supplies) (Scotland) Regulations 2017 if it is to be used for the proposed development.  The development itself shall not be brought into use or occupied until the required supply has been installed in accordance with the recommendations made in the submitted report by Highwater Private Water Supplies – “Spring Water Supply Stronyaraig, near Inverchaolain”, dated 28th November 2018. 

 

Reason:  In the interests of public health and in order to ensure that an adequate private water supply in terms of both quality and quantity can be provided to meet the requirements of the proposed development and to protect existing supplies.

 

3.    No development (including any tree felling or land engineering works or any associated operations) shall take place within the site until the developer has secured the implementation of an archaeological watching brief, to be carried out by an archaeological organisation acceptable to the Planning Authority, during all ground disturbance. The retained archaeological organisation shall be afforded access at all reasonable times and allowed to record, recover and report items of interest and finds. A method statement for the watching brief will be submitted by the applicant, agreed by the West of Scotland Archaeology Service, and approved by the Planning Authority prior to commencement of the watching brief. The name of the archaeological organisation retained by the developer shall be given to the Planning Authority and to the West of Scotland Archaeology Service in writing not less than 14 days before development commences.

 

Reason: In order to allow the recovery and recording of any finds of archaeological significance.

 

4.    The proposed shared vehicular access shall be designed and constructed with a passing place that shall be constructed as per Standard Detail for private driveway SD8004a Access from Single lane road. The access shall be designed and constructed to prevent water running onto the public road. The car parking area shall be designed with a turning area to allow vehicles to exit the site in a forward manner. The access shall be constructed prior to any work commencing on site, unless otherwise agreed in writing by the Planning Authority.

 

Reason:  In the interests of road safety.

 

5.    The dwellinghouse hereby approved shall not be occupied until sightlines of 75 metres from a 2.4 metre setback onto the C10 serving the new domestic curtilage to the north of the church site have been provided. Thereafter, no obstruction to visibility (i.e. walls, fences and hedges) shall be permitted within these visibility splays above a height of 1.0 metre from ground level.

 

      Reason:  To achieve and maintain required sightlines onto the C10 road.

 

6.    Prior to the first occupation of the dwellinghouse, a parking area for a minimum of four vehicles shall be provided within the application site (i.e. land  ...  view the full minutes text for item 5

: