Programme of street lighting capital works 2023/24
Last updated – 1st September 2023
Argyll Street Car Park / Pier Esplanade - £1,500 - 12No. 8M Column Brackets Single Head, 12No. 8m Column Brackets Double Head, Install 2No. 4m Columns and 56No. New LED Luminaires
5 Days – APRIL - In progress (Costs of 56 x LEDs included elsewhere)
Ladside Road and Ladeside Place Rothesay - £66,000 - Column (18No.) and HDU / Cabling Replacement
25 Days – JUNE - Complete
St Brides Road / Blain Terrace Ballochgoy Rothesay - £42,000 - Column (12No.) and Cable Replacement
20 Days – JUNE - Complete
A815 Innellan Shore Road - £204,600 -Column (60No.) and HDU (6No.) / Cabling Replacement
45 Days – OCTOBER - Not yet started
Rosedale Gardens -£26,500- Column (7No.) and HDU Replacement / cabling and ducting
15 Days – JUNE - In progress
Eastwood Lane From the A814 - £32,200 - Column (9No.) and Cable Replacement / Cabling and ducting
15 Days – SEPTEMBER - Not yet started
Kathleen Park (From Rhu Road Higher) - £43,200 - Column (12No.) and HDU / Cabling Replacement
20 Days – JUNE - Complete
Kilmahew Drive & Kilmahew Grove Cardross - £72,000 - Column (20No.) and Cable Replacement
25 Days – NOVEMBER - Not yet started
St Modens Way - £54,200 - Column (15No.) and HDU Replacement
20 Days – DECEMBER - Not yet started
Mull - Back Brae - £73,200 - Column (20no.) 2 x HDU and Cabling Replacement-Contractor
25 Days – OCTOBER - Not yet started
Lorn - Nant Drive / Etive Gardens / Coe Gardens / Ure Gardens / Crecan Gardens / Lonan Drive / Orchy Gardens (PH 1 £128k - 2022) - £238,700 - Column (71No) 8 HDU and cable replacement
90 Days – NOVEMBER - Not yet started
Estimated value of works - £854,100
Various locations - Cat 4 Columns - LED mop up-£180,000-200 nr Column replacement & LED
40 Days – SEPTEMBER - Not yet started
Various locations - Sweep Through - LED Catch -£100,000-600nr tbc LED REPLACEMENT
35 Days – OCTOBER - Not yet started