Roads Capital Programme - Surfacing

Our Roads Capital Works Programme for surfacing and strategic projects in 2023/24

ROADS CAPITAL RECONSTRUCTION 2023-24 -  PROGRAMME  -  "SURFACING" and "STRATEGIC"  SCHEMES

Balance of £7.2M Budget - after SD & PSD  schemes allowances accounted for

Last update - 1st September 2023

Work descriptions:

  • Patching - Removal and replacement of small localised areas of surface layers to existing levels
  • Inlay - Removal and replacement of surface over entire width , where levels fixed by kerbs etc
  • Regulating  - Additional layer of bituminous surfacing to smooth out ruts and potholes , prior to new surface layer
  • Overlay - Additional bituminous surfacing layer over existing to add strength, usually Rural roads
  • Edge Strengthening - Localised widening of carriageway and verge improvements,  prior to surfacing works
  • Geo-grid - Plastic and/or textile reinforcement mat between bituminous layers to resist cracking and deformation
  • Reconstruction - Excavation and replacement of several layers of full width of carriageway structure
  • Pre-Surface Dressing - Minor works to prepare existing surfaces , patching , jet-patching, edge cutting  etc
  • Surface Dressing - Bitumen binder and stone chips - seals surface and improves skid resistance -  over prepared surfaces
Status descriptions

Description

Status

SCHEME PROGRAMMED TO BE DELIVERED - ( Approximate duration and START month indicated )

Not started

SCHEME UNDERWAY - WORK IN PROGRESS -  (Traffic Management as required, during works)

In progress

WORKS ONSITE SUBSTANTIALLY COMPLETE. ( Road Markings and White Lining - Weather permitting )

Complete

Bute and Cowal

Bute

Bute works planned
Road Scheme Name Town Treatment Area  sq.m. Estimate Duration (Days) Start Month (2023) STATUS
UC5 Glecknabae - Pipers Cave Port Bannatyne Resurface 1431  £41,121.91 6 SEPTEMBER Complete
UC5 Glecknabae - Lenihall Port Bannatyne Resurface 1026  £29,483.63 4 SEPTEMBER Complete
A886  Rhubodach Farm Port Bannatyne Overlay 1890  £61,945.95 6 SEPTEMBER Complete
U11   Castle St - Quay St to George St Rothesay Inlay 1800  £57,519.00 5 AUGUST Complete

Bute Total - £109,070.49

Cowal

Cowal works planned
Road Scheme Name Town Treatment Area  sq.m. Estimate Duration (Days) Start Month (2023) STATUS
A815  A886 to Strachur Fire Station Strachur Inlay 3410  £111,870.55 20 JUNE Complete
A815   Rankins Brae to Fir Brae Sandbank Inlay 4298  £137,549.36 25 SEPTEMBER Not started
B8042 Argyll St to Alfred St & A815 to Royal Crescent North  Dunoon Inlay 5785  £181,433.18 3 SEPTEMBER Not started
A8003 View Point  Southwards ( STTS )  Tighnabruaich C/W extension, realigned VSF STTS Bid tbc  £108,817.50 25 AUGUST In progress

Cowal Total - £539,670.50

Bute and Cowal Total - £729,741.07

Helensburgh and Lomond

Helensburgh and Lomond works planned
Road Scheme Name Town Treatment Area  sq.m.  Estimate Duration (Days) Start Month (2023) STATUS
A818 Daligan bends   Helensburgh Resurface  1740  £55,403.70 10 APRIL In progress
U101  E King, Charlotte-  Henry Bell st Helensburgh Inlay 4644  £145,072.62 20 AUGUST Complete
A814 Glen Douglas junction Arrochar Resurface 1711  £45,009.31 10 OCTOBER Not started
A814 North of Glen Douglas Arrochar Resurface 3186  £83,810.43 10 OCTOBER Not started
U004  Adelaide street- East king st to King st crescent Helensburgh inlay 728  £22,832.04 5 AUGUST Complete
U247  Redguantlet rd- Talisman crescent to Endrik Wynd Helensburgh Inlay 960  £30,232.37 10 AUGUST Complete
U259  School road Rhu inlay 1197  £37,560.44 15 JULY Complete
A814  Roundabout at A817/A814 Garelochhead inlay/kerbing 1400  £37,312.00 10 2024 Not started
U053 Camsail road Helensburgh inlay 1472  £45,722.16 10 SEPTEMBER In progress
B833 Altnabui-Mambeg Garelochhead overlay 986  £25,972.43 5 SEPTEMBER Not started
B833 South of Pier-Mambeg Garelochhead Overlay 870  £22,916.85 5 SEPTEMBER Not started
B833  Pier cottage to Mambeg house Garelochhead Overlay 2460  £77,256.30 15 SEPTEMBER Not started
C69 Glen Douglas at Doune Arrochar Resurface 810  £22,913.55 5 OCTOBER Not started

Helensburgh and Lomond Total - £652,014.19

Oban, Lorn and the Isles

Lorn

Lorn works planned
Road Scheme Name Town Treatment Area  sq.m. Estimate Duration (Days) Start Month (2023) STATUS
A816 Loch Nan Druimnean Kilmelford Overlay 1098  £28,809.99 5 JUNE Complete
A816 Arduaine Overlay Arduaine Overlay 3000  £78,815.00 10 OCTOBER In progress
B8003 Cattery to Church Cuan Rd Overlay 900  £25,459.50 1 APRIL Complete
B8045 Area near shop Lismore Overlay 600  £16,973.00 10 SEPTEMBER Not started
B844 Clachandubh Farm Balvicar Overlay 1000  £26,675.00 2 APRIL Complete
B845 Barcaldine to Bonawe Barcaldine Overlay 1800  £50,919.00 3 MAY Complete
C25 Queens Brae North Connel Inlay 1200  £39,006.00 3 SEPTEMBER Not started
C32 Glencruitten Road Oban Inlay 1050  £34,377.75 3 SEPTEMBER Not started
C33 Lerags Road  Oban Overlay 900  £25,459.50 2 APRIL Complete
U004 Croft Road Oban Inlay 1000  £32,175.00 4 JULY Complete
U10 Ardmaddy Road Balvicar Overlay 900  £25,459.50 2 APRIL Complete
A819 Claddich Bends PH 2    (STTS) Dalmally Earthworks, culvert and C/W extension, realigned VSF STTS Bid tbc  £88,536.25 25 July In progress
A816 Kilninver  - PH 7   ( No - STTS) Kilninver C/W extension, realigned VSF 1500  £148,423.75 15 JUNE Complete
A816 Blaran Ph 4    (No - STTS) Kilmelford Earthworks and C/W extension (O/Lay STTS) 1000  £67,115.00 20 OCTOBER Not started

Lorn Total - £688,204.24

Mull and the Isles

Mull and the Isles works planned
Road Scheme Name Town Treatment Area  sq.m. Estimate Duration (Days) Start Month (2023) STATUS
C 68 Breadalbane Street Wall C/F 2022 Tobermory Retaining Wall , F/W & Ped fence Carried Fwd   £450,000.00 (outwith £7.2M Programme) tbc Unknown Not started
U74 Eorabus  Mull -Ardtun Overlay 900  £25,459.50 1 JUNE Complete
C45 Hill Road Mull -Hill Road Overlay 3000  £84,865.00 3 MAY Complete
U70 Caliach Road Mull - Caliach Overlay 900  £25,459.50 1 MAY Complete
C49 Ardtun (inc  Knockvologan) Mull - Ardtun Overlay 900  £25,459.50 1 JUNE Complete
B8035 Gruline  - Knock Mull - Knock Overlay 2400  £67,892.00 3 MAY Complete
U14 Grasspoint Mull - Grasspoint Overlay 2400  £67,892.00 3 JUNE Complete
U009 Main Street, Dervaig Mull - Dervaig Inlay 1200  £38,346.00 4 SEPTEMBER Complete
B8073 Tobermory to Dervaig Mull - Dervaig Overlay 4500  £127,297.50 5 MAY Complete
B8072 Sorisdale Road Isle of Coll Overlay ( Plus rate) 4950  £247,293.75 12 MAR 24 Not started

Mull and the Isles Total - £709,964.75

Oban, Lorn and the Isles Total - £1,398,168.99

Mid Argyll, Kintyre and the Islands

Mid Argyll

Mid Argyll works planned
Road Scheme Name Town Treatment Area  sq.m. Estimate Duration (Days) Start Month (2023) STATUS
A819 Inveraray -Fish Farm Inveraray  Overlay 2320  £61,111.60 5 JUNE Complete
A819 Electric Cottage Ph3   ( STTS ) Inveraray Edge Strengthening & Drainage STTS Bid tbc  £187,998.25 30 AUGUST In progress
A816 Barrichbeyan PH2   (STTS) Craobh Haven Regulate and Surface -  C/W widening (STTS) STTS Bid tbc  £93,286.05 20 AUGUST Complete

Mid Argyll Total - £342,395.90

Kintyre

Kintyre works planned
Road Scheme Name Town Treatment Area  sq.m. Estimate Duration (Days) Start Month (2023) STATUS
A8001 Claonaig  ( slip site) C/F 2022  Skipness Earthworks and CW surfacing Carried Fwd   £342,000.00 (outwith £7.2m programme) tbc 2024 TBC Not started
U13 Macharioch   Southend Overlay 2201  £63,234.63 10 JULY Complete
B843 Revised Drumlemble-Stewarton Machrihanish Overlay 1100  £29,100.50 6 JULY Complete
Burnbank St Burnbank St Campbeltown Inlay 1002  £31,519.75 5 JUNE Complete
Burnside St Burnside Sq to Longrow Campbeltown Inlay 454  £14,263.13 3 JUNE Complete
Bolgam St Bolgam St Campbeltown Inlay 543  £17,080.54 3 JUNE Complete
Castlehill Revised Castlehill  - 2 sections Campbeltown Inlay 1322  £41,556.77 6 JUNE Complete
Range Rd Range Rd Campbeltown Inlay 857  £26,941.46 4 JUNE Complete
U33 Woodlands Dr Campbeltown Inlay 672  £21,130.56 4 JUNE Complete
U 16 Kilypole timber route  (STTS) Machrihanish Resurfacing and drainage STTS Bid tbc  £25,306.19 20 JULY Complete

Kintyre Total - £270,133.52

Islands

Islands works planned
Road Scheme Name Town Treatment Area  sq.m. Estimate Duration (Days) Start Month (2023) STATUS
A846 Corrary Hill to Island House Islay-Bowmore Resurface - Overlay 5249  £167,134.50 20 MAY 24 Not started
C12 S of Barr to W of Cattadale Islay-Ballygrant Resurface - Overlay 2800  £95,414.00 15 MAY 24 Not started

Island Total - £262,548.50