Our footways and kerbs maintenance programme for 2023/24
Capital funding - 2023 footway and kerb maintenance works - existing locations
Construction programme , scheme list 2023 , plus carry-over "active travel / street lighting combined" schemes 2022
Budget - £750,000
Programme status key:
Sequencing and scheme start dates may vary, programme will be updated on a monthly basis, status shows most up to date information available.
Last updated - 1st September 2023
2022/23 Carry over schemes
ACTIVE TRAVEL £500K-2022- FOOTWAY SCHEMES -Carry Over
Woodside Carradale – Kintyre- £53,766.67 - 25 days
JANUARY - Not yet started
CAPITAL ALLOCATION £750K - 2023 SCHEMES
Tomaig Road Footway - With Flooding reinstatement-£60,000.00-15 Days
NOVEMBER - Not yet started
Bruichladdich - Kerbing and surfacing ( Co Funding tbc ?) - £45,000.00 – 20 Days
OCTOBER - Not yet started
Bowmore - Slurry Seal - -£30,000.00 – 15 Days
JULY - Complete
2022/23 Carry over schemes
ACTIVE TRAVEL £500K-2022- FOOTWAY SCHEMES -Carry Over
Nant Drive & Spur Roads - ( in conjunction with Street Lighting) - £50,250.00 - 25 Days
January 24 - Not yet started
CAPITAL ALLOCATION £750K - 2023 SCHEMES
Oban - Dunollie Various - Kerb replacement and surfacing - £29,750.00 -10 Days
JULY - Complete
Oban - Miller Road - Slab replacement - £27,000.00 – 10 Days
JULY - Complete
Mull - Bunessan Phase 2 - £30,000.00 – 15 Days
OCTOBER - Not yet started
Mull - Tobermory - Prison Brae - £28,000.00 – 15 Days
SEPTEMBER - Not yet started
2022/23 Carry over schemes
ACTIVE TRAVEL £500K-2022- FOOTWAY SCHEMES - Carry Over
Cowal
A815 Alexandra Parade FW – Dunoon - £10,751.56 – 10 Days
SEPTEMBER - Not yet started
Lighting Schemes
Rothesay –
Blain Terrace - (in conjunction with Street Lighting) - £18,007.86 – 5 Days
JULY - Complete
Ladeside Road & Place - (in conjunction with Street Lighting) - £19,698.50 – 5 Days
SEPTEMBER - Not yet started
St Brides Road - (in conjunction with Street Lighting) - £20,405.50 -5 Days
JUNE - Complete
Innellan -
Innellan Shore Road - (in conjunction with Street Lighting ) - £26,830.76 - 25 Days
DECEMBER - Not yet started
CAPITAL ALLOCATION £750K - 2023 SCHEMES
Bute
B881 High St - Ministers Brae to Stuart St - various sections - £54,900.00 – 35 Days
SEPTEMBER - Not yet started
A844 Marine Road - St Bruoc to Quay St - £12,200.00 – 10 Days
OCTOBER - Not yet started
B878 Barone Rd - Extension - to cemetery gate - £35,600.00 – 15 Days
OCTOBER - Not yet started
Cowal
A815 Bullwood Rd PH2 - Kilmoray to Sunny brae – westside - £14,600.00 – 6 Days
OCTOBER - Not yet started
A885 Argyll St - Stadium to Bencorrum - East side - £13,000.00 – 6 Days
JULY - Complete
UC01 Ardenslate Rd Ph 3 Bencorrum to Dixon - both sides - £30,000.00 – 20 Days
JULY - Complete
UC08 Bencorrum Brae - A815 to " no1 " - Westside - £6,000.00 – 5 Days
JULY - Complete
UC25 Edward St - Auchamore to William - Eastside - £7,500.00 – 5 Days
OCTOBER - Not yet started
UC48 King St - Jessie to McArthur - Westside - £8,700.00 – 5 Days
OCTOBER - Not yet started
Eleanor Lane - Innellan - £35,000.00 – 20 Days
OCTOBER - Not yet started
UC44 John St - Argyll to Victoria – Southside - £6,000.00 – 5 Days
OCTOBER - Complete
UC28 Ferry Brae - School to Argyll - Southside - £6,000.00 – 5 Days
OCTOBER - Complete
UC16 Clyde Street, Kirn - A815 to Hunter - Southside - £18,000.00 – 10 Days
OCTOBER - Complete
2022/23 Carry over schemes
ACTIVE TRAVEL £500K-2022- FOOTWAY SCHEMES -Carry Over
Guy Mannering, Talisman , Jeanie Deans & Redguantlet FWs -£ 13,788.74 – 5 Days
SEPTEMBER - Not yet started
A814 Colgrain - linking footpaths to above streets - £22,949.50 – 5 Days
SEPTEMBER - Not yet started
Street Lighting combined schemes
Rosedale Gardens (in conjunction with Street Lighting Tracking) - £9,149.00 – 5 Days
JUNE - In progress
Kilmahew Drive (in conjunction with Street Lighting Tracking ) - £11,479.00 – 5 Days
OCTOBER - Not yet started
St Modens Way (in conjunction with Street Lighting Tracking) - £6,202.00 – 5 Days
OCTOBER - Not yet started
CAPITAL ALLOCATION £750K - 2023 SCHEMES
Helensburgh - Dalmore Cres PH 2 other side to completion - £30,000.00 -20 Days
JANUARY - Not yet started
Cardross - A814 PH2 Completion to Crematorium Entrance - £35,750.00 – 25 Days
JANUARY - Not yet started
Faslane A814 Ph 2 Summit to South Gate Junction - £62,000.00 – 30 Days
FEBRUARY - Not yet started
Colgrain PH2 Guy Mannering and Jeanie Deans - £50,000.00 – 25 Days
SEPTEMBER - Not yet started
Clynder - Straid Bheag and Straid a Cnoc- £32,700.00 – 35 Days
MARCH 2024 - Not yet started
Helensburgh - West King Street (James St - Sinclair St) - £26,100.00 – 15 Days
MARCH 2024- Not yet started
Helensburgh - Grant Street (East King St - East Argyle St) - £16,200.00 – 15 Days
MARCH 2024 - Not yet started