Roads Capital Programme - Footways

Our footways and kerbs maintenance programme for 2023/24

Capital funding - 2023 footway and kerb maintenance works - existing locations

Construction programme , scheme list 2023 , plus carry-over "active travel / street lighting combined" schemes 2022

Budget - £750,000

Programme status key:

  • SCHEME PROGRAMMED TO BE DELIVERED - ( Approximate duration and START date indicated ) - Not yet started
  • SCHEME UNDERWAY - WORK In progress - (Traffic Management and Pedestrian access, during works) - In progress
  • WORKS ONSITE SUBSTANTIALLY COMPLETE. ( Footway returned to regular use - minor obstructions only) - Complete

Sequencing and scheme start dates may vary, programme will be updated on a monthly basis, status shows most up to date information available.

Last updated - 1st September 2023

Mid Argyll, Kintyre and the Islands

2022/23 Carry over schemes

ACTIVE TRAVEL £500K-2022- FOOTWAY SCHEMES -Carry Over
Woodside Carradale – Kintyre-  £53,766.67 - 25 days
JANUARY -
Not yet started

CAPITAL ALLOCATION £750K - 2023 SCHEMES
Tomaig Road Footway  - With Flooding reinstatement-£60,000.00-15 Days
NOVEMBER - Not yet started

Bruichladdich -  Kerbing and surfacing  ( Co Funding  tbc ?) - £45,000.00 – 20 Days
OCTOBER - Not yet started

Bowmore - Slurry Seal - -£30,000.00 – 15 Days
JULY - Complete

  • 18% of footway inventory
  • Mid Argyll, Kintyre and the Islands Total - £135,000

Oban, Lorn and the Isles

2022/23 Carry over schemes

ACTIVE TRAVEL £500K-2022- FOOTWAY SCHEMES -Carry Over
Nant Drive & Spur Roads - ( in conjunction with Street Lighting) - £50,250.00 - 25 Days
January 24 - Not yet started

CAPITAL ALLOCATION £750K - 2023 SCHEMES
Oban  - Dunollie Various  - Kerb replacement and surfacing - £29,750.00 -10 Days
JULY - Complete

Oban  -  Miller Road - Slab replacement - £27,000.00 – 10 Days
JULY - Complete

Mull - Bunessan Phase 2 - £30,000.00 – 15 Days
OCTOBER - Not yet started

Mull - Tobermory  - Prison Brae - £28,000.00 – 15 Days
SEPTEMBER - Not yet started

  • 15.3% of footway inventory
  • Oban, Lorn and the Isles Total - £114,750

Bute and Cowal

2022/23 Carry over schemes

ACTIVE TRAVEL £500K-2022- FOOTWAY SCHEMES - Carry Over

Cowal
A815 Alexandra Parade FW – Dunoon - £10,751.56 – 10 Days
SEPTEMBER - Not yet started

Lighting Schemes

Rothesay –
Blain Terrace - (in conjunction with Street Lighting) - £18,007.86 – 5 Days
JULY - Complete

Ladeside Road & Place  - (in conjunction with Street Lighting) - £19,698.50 – 5 Days
SEPTEMBER - Not yet started

St Brides Road - (in conjunction with Street Lighting) - £20,405.50 -5 Days
JUNE - Complete

Innellan -
Innellan Shore Road - (in conjunction with Street Lighting ) - £26,830.76 - 25 Days
DECEMBER - Not yet started

CAPITAL ALLOCATION £750K - 2023 SCHEMES

Bute
B881 High St  -  Ministers Brae to Stuart St - various sections - £54,900.00 – 35 Days
SEPTEMBER - Not yet started

A844 Marine Road - St Bruoc to Quay St - £12,200.00 – 10 Days
OCTOBER - Not yet started

B878 Barone Rd - Extension  - to cemetery gate - £35,600.00 – 15 Days
OCTOBER - Not yet started

Cowal

A815 Bullwood Rd   PH2 - Kilmoray to Sunny brae – westside - £14,600.00 – 6 Days
OCTOBER - Not yet started

A885 Argyll St - Stadium to Bencorrum  - East side - £13,000.00 – 6 Days
JULY - Complete

UC01 Ardenslate Rd Ph 3    Bencorrum to Dixon - both sides - £30,000.00 – 20 Days
JULY - Complete

UC08 Bencorrum Brae -  A815 to " no1 "  - Westside - £6,000.00 – 5 Days
JULY - Complete

UC25 Edward St - Auchamore to William  - Eastside - £7,500.00 – 5 Days
OCTOBER - Not yet started

UC48 King St -  Jessie to McArthur  - Westside - £8,700.00 – 5 Days
OCTOBER - Not yet started

Eleanor Lane - Innellan - £35,000.00 – 20 Days
OCTOBER - Not yet started

UC44 John St - Argyll to Victoria – Southside - £6,000.00 – 5 Days
OCTOBER - Complete

UC28 Ferry Brae -  School to Argyll  - Southside - £6,000.00 – 5 Days
OCTOBER - Complete

UC16 Clyde Street, Kirn - A815 to Hunter  - Southside - £18,000.00 – 10 Days
OCTOBER - Complete

  • 33% of footway inventory
  • Bute and Cowal Total - £247,500

Helensburgh and Lomond

2022/23 Carry over schemes

ACTIVE TRAVEL £500K-2022- FOOTWAY SCHEMES -Carry Over
Guy Mannering, Talisman , Jeanie Deans & Redguantlet  FWs -£ 13,788.74 – 5 Days
SEPTEMBER -  Not yet started

A814 Colgrain - linking footpaths to above streets - £22,949.50 – 5 Days
SEPTEMBER - Not yet started

Street Lighting combined schemes

Rosedale Gardens   (in conjunction with Street Lighting Tracking) - £9,149.00 – 5 Days
JUNE - In progress

Kilmahew Drive  (in conjunction with Street Lighting Tracking ) - £11,479.00 – 5 Days
OCTOBER - Not yet started

St Modens Way   (in conjunction with Street Lighting Tracking) - £6,202.00 – 5 Days
OCTOBER - Not yet started

CAPITAL ALLOCATION £750K - 2023 SCHEMES
Helensburgh -   Dalmore Cres   PH 2  other side to completion - £30,000.00 -20 Days
JANUARY - Not yet started

Cardross - A814 PH2  Completion to Crematorium Entrance - £35,750.00 – 25 Days
JANUARY - Not yet started

Faslane  A814 Ph 2    Summit  to South Gate Junction - £62,000.00 – 30 Days
FEBRUARY - Not yet started

Colgrain PH2   Guy Mannering and Jeanie Deans - £50,000.00 – 25 Days
SEPTEMBER - Not yet started

Clynder - Straid Bheag and Straid a Cnoc- £32,700.00 – 35 Days
MARCH 2024 - Not yet started

Helensburgh - West King Street (James St - Sinclair St) - £26,100.00 – 15 Days
MARCH 2024- Not yet started

Helensburgh - Grant Street (East King St - East Argyle St) - £16,200.00 – 15 Days
MARCH 2024 - Not yet started

  • 33.7% of footway inventory
  • Helensburgh and Lomond Total - £252,750