Roads Capital Programme 2023/24

Our surface dressing programme for 2023/24

Roads Capital Reconstruction Programme 2023/24 - Surface Dressing

  • Planned Network Treatment length Km = 83.644km
  • Equivalent Percentage of Adopted Roads = 3.7%
  • Capital Budget Value = £3,742,332
  • Surface Dressing (SD) Laying Budget = £2.5m
  • Estimated Contract Value = £2,502,767.40

Latest update - 1st September 2023

Programme Status Key

Programme status key
Description Status
SCHEME PROGRAMMED TO BE DELIVERED - ( Approximate duration and START month indicated ) Not started
SCHEME UNDERWAY - WORK IN PROGRESS -  (Traffic Management as required, during works) In progress
WORKS ONSITE SUBSTANTIALLY COMPLETE. ( Road Markings and White Lining - Weather permitting ) Complete

Bute and Cowal

Bute

Bute Surface Dressing 2023/24
Road Scheme Name - Double Surface Dress  SD Area  sq.m.  Pre-SD  /  SD  Estimates Duration (Days) Start Month Status
A866 Pre-SD and Lining    £19,686.88 3 May Complete
Rhubodach 2022-23 site heading north 9120 £54,720.00 1 July Complete
B881 Pre-SD and Lining    £62,780.43 15 May Complete
Meikle Grenach to A844 Scalpsie Jtn 16245 £97,470.00 1 July Complete
  • Bute SD Budget = £150,000
  • Bute total (estimate) - £152,190

Cowal

Cowal Surface Dressing 2023/24
Road Scheme Name - Double Surface Dress  SD Area  sq.m.  Pre-SD  /  SD  Estimates Duration (Days) Start Month Status
A815 Pre-SD and Lining    £13,100.36 3 May Complete
Strachur - Sawmill to Fire Station 7020 £42,120.00 1 July Complete
A815 Pre-SD and Lining    £21,117.52 5 April Complete
Rashfield to Orchard 7020 £42,120.00 1 July Complete
A815 Pre-SD and Lining    £24,048.35 5 May Complete
Ardhallow to Cluniter House 14250 £85,500.00 1 July Complete
A815  Pre-SD and Lining    £24,514.05 5 May Complete
Cluniter Point to Pier Road -  Innellan 9000 £54,000.00 1 July Complete
A885 Pre-SD and Lining    £28,696.27 6 May Complete
A815 to Bencorum Brae 15950 £95,700.00 1 July Complete
A8003 Pre-SD and Lining    £11,115.19 3 May Complete
A886 to North Lodge 4800 £28,800.00 1 July Not started
  • Cowal SD Budget = £350,000
  • Cowal total (estimate) = £348,240
  • Bute and Cowal total (estimate) = £500,430

Helensburgh and Lomond

Helensburgh and Lomond Surface Dressing 2023/24
Road Scheme Name - Double Surface Dress  SD Area  sq.m.  Pre-SD  /  SD  Estimates Duration (Days) Start Month Status
U189 Pre-SD and Lining    £10,417.36 3 April Complete
 Lineside walk 2508 £15,045.00 1 June Complete
U170 Pre-SD and Lining    £9,163.12 3 April Complete
Kidston drive 3402 £20,412.00 1 July Complete
U081 Pre-SD and Lining    £6,205.71 2 April Complete
Cumberland Avenue 2304 £13,824.00 1 July Complete
U228 Pre-SD and Lining    £26,592.84 10 April Complete
Luss to A82 14400 £86,400.00 1 July Complete
B833 Pre-SD and Lining    £22,160.70 8 April Complete
Mill Brae 12000 £72,000.00 1 June Complete
U237 Pre-SD and Lining    £20,804.62 6 June  Complete
Portincaple road 5700 £34,200.00 1 June Complete
U244 Pre-SD and Lining    £20,743.24 6 June  Complete
Red Road 7700 £46,200.00 1 June Complete
U237 Pre-SD and Lining    £27,343.36 10 June  Complete
Darleith Road 10150 £60,900.00 1 June Complete
  • Helensburgh and Lomond SD Budget = £350,000
  • Helensburgh and Lomond total (estimate) = £348,981.00

Oban, Lorn and the Isles

Lorn

Lorn Surface Dressing 2023/24
Road Scheme Name - Double Surface Dress  SD Area  sq.m.  Pre-SD  /  SD  Estimates Duration (Days) Start Month Status
C31 Pre-SD and Lining    £50,176.87 12 April Complete
Ardanaesaig Road 16200 £97,200.00 1 August  Complete
B845 Pre-SD and Lining    £9,375.21 2 April Complete
Taychreggan Road 3600 £21,600.00 1 August  Complete
U37 Pre-SD and Lining    £63,661.78 15 April Complete
Glen Creran Road 38300 £229,800.00 1 August Complete
U134 Pre-SD and Lining    £48,766.53 12 April Complete
Loch Creran Road 31740 £190,440.00 1 August Complete
  • Lorn SD Budget =£475,000
  • Lorn total (estimate) = £539,040

Mull and the Isles

Mull and the Isles Surface Dressing 2023/24
Road Scheme Name - Double Surface Dress  SD Area  sq.m.  Pre-SD  /  SD  Estimates Duration (Days) Start Month Status
A848 Pre-SD and Lining    £26,705.70 10 May
Ardnacross to Gulan Dubh 12000 £72,000.00 1 August Complete
A849 Pre-SD and Lining    £24,926.78 9 May Complete
Salen to Glen Forsa (Revised location) 32400 £194,400.00 1 August Complete
C47 Pre-SD and Lining    £33,786.32 12 April Complete
Glen Gorm   from B8073 Northwards  10850 £65,100.00 1 August Complete
  • Mull and the Isles SD Budget = £400,000
  • Mull and the Isles total (estimate) = £331,500
  • Oban, Lorn and the Isles SD Budget = £875,000
  • Oban, Lorn and the Isles total (estimate) = £870,540

Mid Argyll, Kintyre and the Islands

Mid Argyll

Mid Argyll Surface Dressing 2023/24
Road Scheme Name - Double Surface Dress  SD Area  sq.m.  Pre-SD  /  SD  Estimates Duration (Days) Start Month Status
A816 Pre-SD and Lining    £63,665.03 15 April Complete
Kilmartin-Carnassarie 19720 £118,320.00 1 July Complete
B8024 Pre-SD and Lining    £110,199.53 20 April Complete
South of Middle Hill -Ormsary House 22680 £136,080.00 1 July Complete
  • Mid Argyll SD Budget = £250,000
  • Mid Argyll total (estimate) = £254,400

Kintyre

Kintyre Surface Dressing 2023/24
Road Scheme Name - Double Surface Dress  SD Area  sq.m.  Pre-SD  /  SD  Estimates Duration (Days) Start Month Status
B842 Pre-SD and Lining    £14,447.99 6 April Complete
  Second half - Killellen to Achnaglach . 3360 £20,160.00 1 July Complete
C19 Pre-SD and Lining    £152,303.40 25 April Complete
  Between Kilkerran Rd & Fachoig 26233 £157,399.20 1 July Complete
B879 Pre-SD and Lining    £7,855.19 2 April Complete
  B879 junc to Network Centre.   2268 £13,608.00 1 July Complete
C20 Pre-SD and Lining    £39,915.14 16 April Complete
  Between new Bridge & Arnicle. 10203 £61,219.20 1 July Complete
  • Kintyre SD Budget = £250,000
  • Kintyre total (estimate) = £252,386.40

Islands

Islands Surface Dressing 2023/24
Road Scheme Name - Double Surface Dress  SD Area  sq.m.  Pre-SD  /  SD  Estimates Duration (Days) Start Month Status
B8016 Pre-SD and Lining    £79,889.91 25 April Complete
  Glenegedale northwards 14875 £89,250.00 1 July Complete
C17 Pre-SD and Lining    £48,768.30 20 April Complete
  Uc26 junction to S of Upper Cragabus 8400 £50,400.00 1 July 24 Complete
Uc34 Pre-SD and Lining    £29,260.98 15 April Complete
  S of Craigens Cottage N of Bun an Uilt 5040 £30,240.00 1 July 24 Not started
Uc14 Pre-SD and Lining    £23,571.35 14 April Complete
  A846 junction to  track to East Lodge  4060 £24,360.00 1 July 24 Not started
A847 Pre-SD and Lining    £63,798.62 24 April Complete
  West of Bridgend 13630 £81,780.00 1 July Complete
  • Islands SD Budget = £275,000
  • Islands total (estimate) = £276,030
  • Mid Argyll, Kintyre and the Islands budget = £775,000
  • Mid Argyll, Kintyre and the Islands total (estimate) = £782,816.40