Latest update - 1st September 2023
Description | Status |
SCHEME PROGRAMMED TO BE DELIVERED - ( Approximate duration and START month indicated ) | Not started |
SCHEME UNDERWAY - WORK IN PROGRESS - (Traffic Management as required, during works) | In progress |
WORKS ONSITE SUBSTANTIALLY COMPLETE. ( Road Markings and White Lining - Weather permitting ) | Complete |
Road | Scheme Name - Double Surface Dress | SD Area sq.m. | Pre-SD / SD Estimates | Duration (Days) | Start Month | Status | ||
---|---|---|---|---|---|---|---|---|
A866 | Pre-SD and Lining | £19,686.88 | 3 | May | Complete | |||
Rhubodach 2022-23 site heading north | 9120 | £54,720.00 | 1 | July | Complete | |||
B881 | Pre-SD and Lining | £62,780.43 | 15 | May | Complete | |||
Meikle Grenach to A844 Scalpsie Jtn | 16245 | £97,470.00 | 1 | July | Complete |
Road | Scheme Name - Double Surface Dress | SD Area sq.m. | Pre-SD / SD Estimates | Duration (Days) | Start Month | Status |
---|---|---|---|---|---|---|
A815 | Pre-SD and Lining | £13,100.36 | 3 | May | Complete | |
Strachur - Sawmill to Fire Station | 7020 | £42,120.00 | 1 | July | Complete | |
A815 | Pre-SD and Lining | £21,117.52 | 5 | April | Complete | |
Rashfield to Orchard | 7020 | £42,120.00 | 1 | July | Complete | |
A815 | Pre-SD and Lining | £24,048.35 | 5 | May | Complete | |
Ardhallow to Cluniter House | 14250 | £85,500.00 | 1 | July | Complete | |
A815 | Pre-SD and Lining | £24,514.05 | 5 | May | Complete | |
Cluniter Point to Pier Road - Innellan | 9000 | £54,000.00 | 1 | July | Complete | |
A885 | Pre-SD and Lining | £28,696.27 | 6 | May | Complete | |
A815 to Bencorum Brae | 15950 | £95,700.00 | 1 | July | Complete | |
A8003 | Pre-SD and Lining | £11,115.19 | 3 | May | Complete | |
A886 to North Lodge | 4800 | £28,800.00 | 1 | July | Not started |
Road | Scheme Name - Double Surface Dress | SD Area sq.m. | Pre-SD / SD Estimates | Duration (Days) | Start Month | Status |
---|---|---|---|---|---|---|
U189 | Pre-SD and Lining | £10,417.36 | 3 | April | Complete | |
Lineside walk | 2508 | £15,045.00 | 1 | June | Complete | |
U170 | Pre-SD and Lining | £9,163.12 | 3 | April | Complete | |
Kidston drive | 3402 | £20,412.00 | 1 | July | Complete | |
U081 | Pre-SD and Lining | £6,205.71 | 2 | April | Complete | |
Cumberland Avenue | 2304 | £13,824.00 | 1 | July | Complete | |
U228 | Pre-SD and Lining | £26,592.84 | 10 | April | Complete | |
Luss to A82 | 14400 | £86,400.00 | 1 | July | Complete | |
B833 | Pre-SD and Lining | £22,160.70 | 8 | April | Complete | |
Mill Brae | 12000 | £72,000.00 | 1 | June | Complete | |
U237 | Pre-SD and Lining | £20,804.62 | 6 | June | Complete | |
Portincaple road | 5700 | £34,200.00 | 1 | June | Complete | |
U244 | Pre-SD and Lining | £20,743.24 | 6 | June | Complete | |
Red Road | 7700 | £46,200.00 | 1 | June | Complete | |
U237 | Pre-SD and Lining | £27,343.36 | 10 | June | Complete | |
Darleith Road | 10150 | £60,900.00 | 1 | June | Complete |
Road | Scheme Name - Double Surface Dress | SD Area sq.m. | Pre-SD / SD Estimates | Duration (Days) | Start Month | Status |
---|---|---|---|---|---|---|
C31 | Pre-SD and Lining | £50,176.87 | 12 | April | Complete | |
Ardanaesaig Road | 16200 | £97,200.00 | 1 | August | Complete | |
B845 | Pre-SD and Lining | £9,375.21 | 2 | April | Complete | |
Taychreggan Road | 3600 | £21,600.00 | 1 | August | Complete | |
U37 | Pre-SD and Lining | £63,661.78 | 15 | April | Complete | |
Glen Creran Road | 38300 | £229,800.00 | 1 | August | Complete | |
U134 | Pre-SD and Lining | £48,766.53 | 12 | April | Complete | |
Loch Creran Road | 31740 | £190,440.00 | 1 | August | Complete |
Road | Scheme Name - Double Surface Dress | SD Area sq.m. | Pre-SD / SD Estimates | Duration (Days) | Start Month | Status |
---|---|---|---|---|---|---|
A848 | Pre-SD and Lining | £26,705.70 | 10 | May | ||
Ardnacross to Gulan Dubh | 12000 | £72,000.00 | 1 | August | Complete | |
A849 | Pre-SD and Lining | £24,926.78 | 9 | May | Complete | |
Salen to Glen Forsa (Revised location) | 32400 | £194,400.00 | 1 | August | Complete | |
C47 | Pre-SD and Lining | £33,786.32 | 12 | April | Complete | |
Glen Gorm from B8073 Northwards | 10850 | £65,100.00 | 1 | August | Complete |
Road | Scheme Name - Double Surface Dress | SD Area sq.m. | Pre-SD / SD Estimates | Duration (Days) | Start Month | Status |
---|---|---|---|---|---|---|
A816 | Pre-SD and Lining | £63,665.03 | 15 | April | Complete | |
Kilmartin-Carnassarie | 19720 | £118,320.00 | 1 | July | Complete | |
B8024 | Pre-SD and Lining | £110,199.53 | 20 | April | Complete | |
South of Middle Hill -Ormsary House | 22680 | £136,080.00 | 1 | July | Complete |
Road | Scheme Name - Double Surface Dress | SD Area sq.m. | Pre-SD / SD Estimates | Duration (Days) | Start Month | Status |
---|---|---|---|---|---|---|
B842 | Pre-SD and Lining | £14,447.99 | 6 | April | Complete | |
Second half - Killellen to Achnaglach . | 3360 | £20,160.00 | 1 | July | Complete | |
C19 | Pre-SD and Lining | £152,303.40 | 25 | April | Complete | |
Between Kilkerran Rd & Fachoig | 26233 | £157,399.20 | 1 | July | Complete | |
B879 | Pre-SD and Lining | £7,855.19 | 2 | April | Complete | |
B879 junc to Network Centre. | 2268 | £13,608.00 | 1 | July | Complete | |
C20 | Pre-SD and Lining | £39,915.14 | 16 | April | Complete | |
Between new Bridge & Arnicle. | 10203 | £61,219.20 | 1 | July | Complete |
Road | Scheme Name - Double Surface Dress | SD Area sq.m. | Pre-SD / SD Estimates | Duration (Days) | Start Month | Status |
---|---|---|---|---|---|---|
B8016 | Pre-SD and Lining | £79,889.91 | 25 | April | Complete | |
Glenegedale northwards | 14875 | £89,250.00 | 1 | July | Complete | |
C17 | Pre-SD and Lining | £48,768.30 | 20 | April | Complete | |
Uc26 junction to S of Upper Cragabus | 8400 | £50,400.00 | 1 | July 24 | Complete | |
Uc34 | Pre-SD and Lining | £29,260.98 | 15 | April | Complete | |
S of Craigens Cottage N of Bun an Uilt | 5040 | £30,240.00 | 1 | July 24 | Not started | |
Uc14 | Pre-SD and Lining | £23,571.35 | 14 | April | Complete | |
A846 junction to track to East Lodge | 4060 | £24,360.00 | 1 | July 24 | Not started | |
A847 | Pre-SD and Lining | £63,798.62 | 24 | April | Complete | |
West of Bridgend | 13630 | £81,780.00 | 1 | July | Complete |