Published Date:
14 Sep 2015 - 14:18
Since the Oban Airport access improvement project started on site last week work has been going well.
We have safely and securely set up the site and have been progressing with the excavation of ground to level the area. As part of the preparatory work we have also removed excess foliage and other associated debris.
Next week we will be moving on to form the road levels and lay a sub-base.