Argyll and Bute council’s getting to work on the roads of Oban, Lorn and the Isles. It’s part of the council’s £15.6 million which will be spent improving the road network over the next three years. £7 million has been earmarked for 2011-12.
The A816 from Oban to Lochgilphead will be resurfaced from Moleigh to Kilmore, at Tullich and at Kames Farm by the end of July this year.
The A819 from Dalmally to Inveraray will be resurfaced at several locations and this work will be completed by Friday 8th July.
On Mull there’ll be resurfacing on the A848 from Tobermory to Salen and Salen to Craignure. On the A849 there’ll be resurfacing between Craignure and Fionnphort.
Executive Director of Development and Infrastructure, Sandy Mactaggart, said “this work will make a real difference to the communities of Oban, Lorn and the Isles. Some of the work has already started and will continue over the summer. The council is committed to improving the area’s roads for local people, businesses and tourists.”
Notes for Editors:
OBAN AND LORN
A816 – Oban to Lochgilphead, Moleigh to Kilmore – regulated and resurfaced – this will take 5 days and is planned from Monday 11th July until Friday 15th July 2011.
A816 – Oban to Lochgilphead, Tullich – regulated and resurfaced – this will take 5 days and is planned from Monday 18th July until Friday 22nd July 2011.
A816 – Oban to Lochgilphead, Kames Farm – regulated and resurfaced – this will take 5 days and is planned from Monday 18th July until Friday 22nd July 2011.
A819 – Dalmally to Inveraray, Ardteastle to Innistrynich – carriageway edge strengthening, carriageway widening, regulate and overlay, drainage improvements – this will take 40 days and is planned from Monday 9th May till Friday 1st July 2001
A819 – Dalmally to Inveraray, various locations – regulate and resurface – this will take 5 days and is planned from Monday 4th July until Friday 8th July
B845 – Taynuilt to Kilchernnan – regulate and resurface – this will take 10 days from Monday 25th July until Friday 5th August 2011.
U22 – Tweedle Street, Oban – planed out, patch, regulate and resurface – this will take 5 days from Monday 2nd May until Friday 6th May 2011.
U41 – Lochavullin Road Oban – Tesco roundabout – plane out, patch, regulate and resurface – this will take 2 days from Sunday 17th April until Monday 18th April 2011.
B844 – Kilniver to Ellanabeich – structural strengthening and surface dressing (no dates available)
B8003- Balvicar to Cuan - structural strengthening and surface dressing (no dates available)
U16 – Armaddy ferry - structural strengthening and surface dressing (no dates available)
U10 – Kilmelford – Auchnasaul, Armaddy castle section - structural strengthening and surface dressing (no dates available)
Ardencaple Road - structural strengthening and surface dressing (no dates available)
MULL
A848 – Eas Brae to Balisgate – plane out, regulate and resurface
A848 – Tobermory to Saline, Gualen Dhubh towards bridge – regulate and resurface
A848 – Salen to Craignure, Balmeanach – regulate and resurface
A848 - Salen to Craignure, Fishnish – regulate and resurface
A849 – Craignure to Fionnphort, Pennygael – regulate and resurface
A849 – Craignure to Fionnphort, Fionnphort – regulate and resurface
B8035 – Kinloch to Balmeanoch – structural strengthening and surface dressing
The dates missing have yet to be decided upon.