Argyll and Bute Council’s getting to work on several roads in Helensburgh and Lomond. It’s part of the council’s £15.6 million which will be spent improving the road network the next three years. £7 million is earmarked for 2011-2012.
There are six roads earmarked for resurfacing work in Helensburgh including Buchanan Road, Colquhoun Street and Glasgow Street. Work will be completed by mid September.
In Lomond four roads in Cardross will be resurfaced by the 1st of July. In Rosneath, Argyll Road has already been fully resurfaced and in Garelochhead, Queens Crescent will be resurfaced by 7TH October.
Executive Director of Development and Infrastructure , Sandy Mctaggart, said “this work will make a real difference to the communities of Helensburgh and Lomond. Some of the work has already started and will continue over the summer. The council is committed to improving the area’s roads for local people, businesses and tourists.”
Notes for Editors:
Here is a full list of roads in the area being worked on by the council;
HELENSBURGH
Buchanan Road, Helensburgh – Athole Street to Ben Bouie Avenue – resurfacing – this will take place over 5 days from 25th July until 29th July.
Stuckleckie Road, Helensburgh – Kirkmichael Road to Ben Bouie Drive – resurfacing – this will take place over 5 days from 1st August until 5th August
Colquhoun Street, Helensburgh – Princes St to King St and W Montrose St to Rossdhu Road – resurfacing – this will take 10 days from 15th August until 26th August
Glasgow Street, Helensburgh – Argyll St to Millig St – resurfacing - this will take 5 days from 29th August until 2nd September
Suffolk Street, Helensburgh – Montrose St to Queen St –resurfacing - this will take 5 days from 5th September until 9th September
West Princes St, Helensburgh – Coulport Place to Fernigair Avenue –resurfacing - this will take 5 days from12th September until 16th September
LOMOND
Peaton Road, Peninsula - resurfacing full length – this will take 10 days from 4th April until 15th April
Argyll Road, Rosneath – resurfacing full length – this will take 5 days from 18th April until 22nd April
Muirend Road – resurfacing full length – this will take 10 days from 25th April until 6th May
Reay Avenue, Cardross – resurfacing full length – this will take 5 days from 23rd May until 27th May
Church Avenue, Cardross – resurfacing full length – this will take 5 days from 30th May until 3rd June
Red Road, Cardross – resurfacing full length – this will take 10 days from 6th June until 17th June
Darlieth Road, Cardross – resurfacing full length – this will take 10 days from 20th June till 1st July
Caldwell Place / Station Road, Rhu – Laggaray Pk to Manse Brae (including 200 m of station road) will take 10 days from 19th September until 30th September
Queens Crescent, Garelochhead – full length resurfacing – this will take 5 days from 3rd October until 7th October.