Report by Head of Development and Economic Growth
Minutes:
The Major Applications Team Leader spoke to
the terms of the report. The proposal
seeks to develop an allocated housing site within LDP2 to provide 97 dwellings
of various sizes. The site is located in
the rural area, with the housing allocation playing a pivotal role in meeting
the housing needs of the island.
The Examination by Scottish Government
Reporters to the Argyll and Bute Local Development Plan 2 (LDP2) has now
concluded and the Examination Report has been published. Although still to be formally adopted it is
considered that LDP2 carries sufficient weight to outweigh the designation of
land as countryside in the adopted LDP.
The development would still be a minor
departure from LDP2 as a small area to the north west of the site lies out with
the allocation and within the countryside zone.
No houses are proposed in this area and it would be required to
accommodate one of the two Sustainable Urban Drainage Areas (SUDs) required for
draining the site.
It was recommended that planning permission
be granted subject to the conditions and reasons detailed in the report of
handling.
Decision
The Committee agreed to grant planning
permission subject to the following conditions and reasons:
1. PP - Approved Details & Standard Notes – Non
EIA Development
The development
shall be implemented in accordance with the details specified on the
application form dated 8/7/22; , supporting information and, the approved
drawings listed in the table below unless the prior written approval of the
planning authority is obtained for an amendment to the approved details under
Section 64 of the Town and Country Planning (Scotland) Act 1997.
Plan Title. |
Plan Ref. No. |
Version |
Date Received |
Location Plan as Existing |
200661A-10-002 |
Rev.D |
06/09/2022 |
Topographical Survey Plan as Existing |
200661A-10003 |
Rev.A |
06/09/2022 |
Location Plan – Craignure Context as
Existing |
200661A-10-001 |
Rev.C |
06/09/2022 |
Location Plan as Proposed |
200661A-PL-001 |
Rev.G |
09/11/2023 |
Site Plan as Proposed |
200661A-PL-003 |
Rev.C |
9/11/2023 |
Site Cross Section Detail as Proposed |
200661A-PL-002 |
Rev.A |
18/08/2022 |
External Levels Layout |
J5336-001 |
|
11/07/2022 |
Drainage Layout |
J5336-011 |
Rev.F |
09/03/2023 |
Cottage Flats- Affordable Plans &
Elevations |
200661A-PL-010 |
Rev.A |
18/08/2022 |
2 & 3 Bed Terrace- AFF. Plans &
Elevations |
200661A-PL-011 |
Rev.B |
06/09/2023 |
3 Bed Semi-Detached –AFF Plans &
Elevations |
200661A-PL-012 |
|
11/07/2022 |
1 Bed Flats- PFS Plans & Elevations |
200661A-PL-013 |
Rev.A |
18/08/2022 |
2 Bed Flats –PFS Plans & Elevations |
200661A-PL-014 |
Rev.A |
18/08/2022 |
2 Bed Bungalow – PFS Plans & Elevations |
200661A-PL-015 |
Rev.A |
18/08/2022 |
3 Bed Flat & Retail Uni- PFS Plans
& Elevations |
200661A-PL-016 |
Rev.B |
05/04/2023 |
3 Bed Semi Detached- PFS Plans &
Elevations |
200661A-PL-017 |
Rev.A |
18/08/2022 |
3 Bed Detached- PFS Plans & Elevations |
200661A-PL-018 |
|
11/07/2022 |
4 Bed Detached- ST- PFS Plans &
Elevations |
200661A-PL-019 |
|
11/07/2022 |
4 Bed Detached In- PFS Plans &
Elevations |
200661A-PL-020 |
|
11/07/2022 |
4 Bed Detached Wide- PFS Plans &
Elevations |
200661A-PL-021 |
Rev.A |
18/08/2022 |
4 Bed Detached Large- PFS Plans &
Elevations |
200661A-PL-022 |
|
11/07/2022 |
2 & 3 Bed Terrace – AFF. Combined Plans |
200661A-PL-023 |
Rev.A |
06/09/2022 |
3 Bed Detached – Handed Plans &
Elevations |
200661A-PL-024 |
|
18/08/2022 |
4 Bed Detached St – Handed Plans &
Elevations |
200661A-PL-025 |
|
18/08/2022 |
4 Bed Detached Inv-Handed Plans &
Elevations |
200661A-PL-026 |
|
18/08/2022 |
4 Bed Detached Wide-Handed Plans &
Elevations |
200661A-PL-027 |
|
18/08/2022 |
4 Bed Detached Large-Handed Plans &
Elevations |
200661A-PL-028 |
|
18/08/2022 |
1 & 2 Bed Flats – PFS Plans &
Elevations |
200661A-PL-029 |
|
06/09/2022 |
Garage Units Plans & Elevations |
200661A-PL-051 |
|
18/08/2022 |
Vehicle Swept Path Analysis for a Refuse
Vehicle |
J5336-004 |
|
11/07/2022 |
Proposed Landscape Layout |
1641-01 |
Rev.F |
18/08/2022 |
Softworks Specification & Maintenance |
1641-03 |
Rev.B |
04/07/2023 |
Proposed trees to be removed & retained |
1641-02 |
Rev.B |
04/07/2023 |
Waste Strategy & Bin Storage |
200661A-PL050 |
Rev.A |
06/09/2022 |
Reason: For the purpose of clarity, to ensure that
the development is implemented in accordance with the approved details.
Note to Applicant:
· This planning permission will last for three years from the date of this
decision notice, unless the development has been started within that period [See
section 58(1) of the Town and Country Planning (Scotland) Act 1997 (as
amended).]
·
In order to comply with Sections 27A(1) of the Town and Country Planning (Scotland)
Act 1997, prior to works commencing on site it is the responsibility of the
developer to complete and submit the attached ‘Notice of Initiation of
Development’ to the Planning Authority specifying the date on which the
development will start. Failure to comply with this requirement constitutes a
breach of planning control under Section 123(1) of the Act.
In order to comply
with Section 27B(1) of the Town and Country Planning (Scotland) Act 1997 it is
the responsibility of the developer to submit the attached ‘Notice of
Completion’ to the Planning Authority specifying the date upon which the
development was completed.
2.
Archaeological
Works
No development
shall take place within the development site as outlined in red on the approved
plan until the developer has secured the implementation of a programme of
archaeological works in accordance with a written scheme of investigation which
has been submitted by the applicant, agreed by the West of Scotland Archaeology
Service, and approved by the Planning Authority. Thereafter the developer shall
ensure that the programme of archaeological works is fully implemented and that
all recording and recovery of archaeological resources within the development
site is undertaken to the satisfaction of the Planning Authority in agreement
with the West of Scotland Archaeology Service.
Reason: In
order to comply with the requirements of NPF4 Policy 16F.
3.
Requirement for
Public Sewerage Connection
The development
hereby approved shall connect to the public sewerage system.
Reason: The site is located within a settlement
area served by a public sewer. The use
of a private system would be a material change and would require the submission
of a further planning application.
4. Open Space Provision
No development shall commence until details for the
provision and maintenance of areas of communal open space and equipped play
area(s) identified on the approved plans have been submitted to and approved in
writing by the Planning Authority. The details shall comprise:
(i)
Provision
to satisfy the minimum standards set out in the Development Plan; 6sqm of
equipped play space and 12sqm of informal open space per dwelling unit;
(ii)
Specification
of play equipment to be installed, including surface treatments and any means
of enclosure, designed in accordance with the provisions of BS5696 (Play
Equipment Intended for Permanent Installation Outdoors);
(iii) Proposals for the timing of the implementation of
the play area(s) in relation to the phasing of the development. The equipped children’s play area shall be
completed before the occupation of the 50th dwelling;
(iv) A maintenance schedule for communal open spaces and
equipped play areas in accordance with the provisions of BS5696 including
details of on-going inspection, recording and procedures for detailing with
defects.
The communal open space and equipped play area(s)
shall be provided in accordance with the duly approved details and shall be
retained and maintained to the specified standards thereafter.
Reason: In order to secure provision of communal
open space and equipped play areas within the development in accordance with
the requirements of NPF4 Policy 16F.
5.
Construction
Environmental Management Plan
No
construction works shall be commenced until a Construction Environmental
Management Plan
(CEMP) and a Site Waste Management Plan (SWMP) have been submitted to and
approved in writing by the Planning Authority. The CEMP shall be overseen
by an Ecological Clerk of Works (ECoW) and shall cover the following details:
Public Protection Issues:
a)
Consideration
of all local noise sensitive receptors and the impact which would be had during
land clearance and construction and the controls for this
b)
The
use of equipment, such as mobile crushers and pecking equipment which may be in
use and the controls which are put in place for these
c)
Any
controls for dust on the site to ensure that this does not cause a nuisance to
nearby receptors
d)
Any
site lighting which may be used during the project and how this will be
controlled so as not to cause a light nuisance to local receptors
e)
Proposed
hours of works
f)
Best
Practical Means measures to be put in place during any land clearance and
construction work phases.
Biodiversity
Issues:
(a)
No development shall commence until a scheme for the retention and safeguarding
of trees during construction has been submitted to and approved by the Planning
Authority. The scheme shall comprise:
i) Details of all
trees to be removed and the location, canopy spread and root zone of trees to
be retained as part of the development;
ii) A programme of
measures for the protection of trees during construction works which shall
include fencing at least one metre beyond the canopy spread taking account of
root zone of each tree in accordance with BS 5837:2012 “Trees in Relation to
Design, Demolition and Construction”.
Tree protection
measures shall be implemented for the full duration of construction works in
accordance with the duly approved scheme. No trees shall be lopped, topped or
felled other than in accordance with the details of the approved scheme unless
otherwise approved in writing by the Planning Authority.
(b)
Prior to the commencement of development an updated habitat survey shall be
carried out, the findings of which shall be submitted to and approved in
writing with the planning authority- this information should form part of a
Habitat Management Plan.
(c)
If tree works are proposed during the bird nesting season (March – August
inclusive) a pre-commencement inspection for active bird nests should be
carried out by a suitably qualified person. Only if there are no active
nests present should works proceed.
(d)
Otter mitigation shall be undertaken in accordance with the recommendations
contained within the original ecological survey for otter
- An ecological toolbox talk will be
presented to all site contractors as part of their pre-works site induction in
accordance with best practice;
- Where the species data is older than 18
months, the reported baseline should be updated by further survey work and
included as part of a Species Management Plan outlining the species management
for each of the species mentioned ( Otter, Bats both European protected
Species, birds ( none specific).
(e)
If any of the trees which have been identified as being suitable for bats are
to be removed between May-September, a further inspection of these trees shall
be carried out by a licensed Bat worker prior to their removal. A European
Protected Species Licence will need to be acquired from NatureScot in order for
the bats to be translocated by a licenced Bat Worker.
(f)
An ecological toolbox talk on bats and what to do if bats or field signs of
bats are encountered shall be presented to all site contractors as part of
their pre-works site induction.
Further information can be found in the Biodiversity Technical Note in terms of
surveys and mitigation calendars Page 20 and 21: https://www.argyll-bute.gov.uk/sites/default/files/biodiversity_technical_note_feb_2017_4.pdf
(i)
An Invasive Non Native Species Eradication Plan for Rhododendron
ponticum should be included in the CEMP ready for implementation.
(j)
Details of pollution controls during
construction.
Reason: In order avoid, minimise or mitigate
effects on the environment and surrounding area.
6.
White Tailed Sea
Eagle
Prior to the commencement
of development confirmation of the outcome of discussions with the Mull RSPB
Officer (currently Dave Sexton) with regard to requirements for a Bird
Protection Plan for White Tailed Eagle shall be submitted to and approved in
writing by the Planning Authority. In the event that a Bird Protection Plan is
required, this shall be submitted to and approved in writing by the Planning
Authority prior to the commencement of development. Thereafter the development shall proceed in
accordance with this plan.
Reason: In order
to establish whether a Bird Protection Plan will be required as the
nesting locations
of White Tailed Sea Eagles varies each year.
7.
Drainage
Maintenance Arrangements
Prior to the
commencement of approved drainage works, details of the maintenance
responsibility and schedule of intended maintenance arrangements of the
approved drainage works shall be provided to the Planning Authority for their
approval. This schedule shall include inspection, recording and procedures for
detailing with defects. For the avoidance of doubt this shall also include the
maintenance of the SUDs ponds. The drainage works for the development shall
thereafter be maintained in accordance with the approved details.
Reason: To ensure appropriate maintenance
provisions in respect of the approved drainage details are secured in the
interests of alleviating any potential flood risk arising from surface
water.
8.
Landscaping
Details
No
development shall commence until a scheme of boundary treatment, surface
treatment and landscaping has been submitted to and approved in writing by the
Planning Authority. The scheme shall comprise a planting plan and schedule
which shall include details of:
i)
Existing and
proposed ground levels in relation to an identified fixed datum;
ii)
Existing
landscaping features and vegetation to be retained;
iii)
Location design
and materials of proposed walls, fences and gates;
iv)
Proposed soft and
hard landscaping works including the location, species and size of every
tree/shrub to be planted;
v)
Details of
compensatory tree planting as show on the proposed landscape drawing produced
by Hirst Landscape Architects (1641 01 rev F).
vi)
A programme for
the timing, method of implementation, completion and subsequent on-going
maintenance.
vii)
Surface materials
proposed for private communal parking areas.
All
of the hard and soft landscaping works shall be carried out in accordance with
the approved scheme unless otherwise approved in writing by the Planning
Authority.
Any
trees/shrubs which within a period of five years from the completion of the
approved landscaping scheme fail to become established, die, become seriously
diseased, or are removed or damaged shall be replaced in the following planting
season with equivalent numbers, sizes and species as those originally required
to be planted unless otherwise approved in writing by the Planning Authority.
Reason: To assist with the integration of the
proposal with its surroundings in the interest of amenity.
9.
Road Built to
Adoptable Standards
All new roads
other than private accesses serving no more than 5 dwellings shall be built to
an adoptable standard in accordance with Designing Streets and the National
Roads Development Guide.
Reason: In the interests of road safety to ensure
the provision of a road commensurate to the scale of development.
10.
20mph Speed Limit
Within 12 months
of the occupation of the first dwelling house the internal road network shall
have a 20mph limit.
Reason: In the interests of road safety.
11.
Junction
Improvements
Full details of
improvements to the existing junction of the UC80 and the A849 shall be
submitted to and approved in writing by the Planning Authority in consultation
with the Road Network Manager. This
shall include resurfacing of the UC80 east footway from the junction of the
development to the A849.
Reason: In the interests of road safety.
12.
Visibility Splays
Prior to work
starting on site the junction of the development access with the UC80 shall
have a visibility splay of 42m x 2.4m x 1.05m.
The final wearing surface on the access shall be completed prior to the
development first being brought into use and the visibility splays shall be
maintained clear of all obstructions thereafter.
Reason: In the interests of road safety.
13.
40mph Speed Limit
No development
shall commence until a 40mph speed limit is introduced on the A849 from the
existing 30mph limit at Craignure to an agreed location west of the UC80. Prior to the implementation of this speed
limit full details of the extent of the speed limit shall be submitted to and
approved in writing by the Planning Authority in consultation with the Road
Network Manager.
Reason: In the interests of road safety.
14.
Traffic Management
Plan
Prior to
development commencing, a Traffic Management Plan shall be submitted to and
approved in writing by the Planning Authority in consultation with the Area
Roads Engineer. The Plan shall detail the phasing of the construction elements
of the development, a proposed phasing schedule of the plant and materials
deliveries to site, proposed and approved access routes, agreed operational
practices, and shall provide for the provision of an appropriate Code of
Practice to drivers of construction and delivery vehicles. The development
shall be implemented in accordance with the duly approved Traffic Management
Plan unless as otherwise may be agreed in writing by the Area Roads Engineer.
Reason: To
address traffic associated with the construction of the development in the
interests of road safety and having regard to the access arrangements to the
site.
15.
Electric Vehicle
Charging
Prior to any
dwelling being occupied which has private in-curtilage parking provision, dedicated cable ducting connecting each private
residential parking space to the nearest electricity supply connection point
capable of supporting the installation of a 7 kilowatt EV charging point shall
be provided.
Prior to dwellings
being occupied where communal parking is proposed, a minimum of one EV charging
point for every five residential communal off street spaces shall be
provided. In addition, dedicated cable
ducting shall be installed to allow all remaining communal parking spaces to be
provided with a charging point in the future.
Reason: To ensure that the development has adequate
provision for the charging of EVs in accordance with policy 34 of LDP2.
16.
Biodiversity
Enhancement Measures
Biodiversity
enhancement measures shall be undertaken in accordance with the Biodiversity
Measures document dated 11th July 2023. Prior to the occupation of the first dwelling
further details of the proposed enhancements as detailed in this document
including their design, location and timing of completion shall be submitted to
and approved in writing by the Planning Authority. Thereafter these biodiversity enhancement
shall by maintained in accordance with these details.
Reason: To
ensure that the development includes biodiversity enhancements as required by
NPF4 Policy 3.
17.
No Permission for
Care Home or Nursery
No permission is
given or implied for the proposed nursery or care home shown indicatively on
the approved site plan.
Reason: For
the avoidance of doubt.
18.
Hours of
Construction
The permitted
hours of construction works shall be restricted to 08:00 hours to 18:00 hours
Monday to Friday and 08:00 hours to 13:00 hours on Saturday. No construction
works shall take place outwith these hours, or on Sundays or Bank Holidays,
unless the written agreement of the Planning Authority has been obtained in
advance, in which case the specified operations shall be confined to activities
which do not present any likely source of nuisance in terms of noise,
vibration, dust or any other consequence likely to be prejudicial to the
interests of residential amenity.
Reason: In order to protect the residential amenities of the area.
19.
Affordable Housing
Plots 74 to 97 shall
only be managed by a Registered Social Landlord (a body registered under part 3
chapter 1 of the Housing (Scotland) Act 2001, or any equivalent provision in
the event of the revocation and re-enactment thereof, with or without
modification) and shall not enure for the benefit of any other person, company
or organisation.
Reason: To ensure the provision of affordable housing
to the standard required by the development plan in the absence of any other
agreed means of securing such provision.
20.
Materials
No development
shall commence until full details /samples of materials to be used in the
construction of the dwelling houses and commercial unit hereby approved have
been submitted to and approved in writing by the Planning Authority. The development shall thereafter be completed
using the approved materials or such alternatives as may be agreed in writing
with the Planning Authority.
Reason: In
order to integrate the development into its surroundings.
21.
Arrangements for
Waste
No
development shall commence until a waste strategy detailing how much waste
the proposal is
expected to generate and detailing the arrangements for the storage, separation
and collection of waste from the site, including provision for the safe pick
up by refuse
collection vehicles, have been submitted to an approved in writing by the
Planning Authority. Thereafter the duly approved provision shall be implemented
prior to the first occupation of the dwellings which it is intended to serve.
Reason: In
order to ensure that satisfactory arrangements have been made for dealing with
waste on the site in accordance with NPF4 Policy 12 and Policy SG LDP SERV 5
(b).
22.
Finished Floor
Levels
No
development shall commence until details of the proposed finished ground floor
level
of the development relative to an identifiable fixed datum located outwith the
application
site have been submitted to and approved in writing by the Planning
Authority.
The development shall be implemented in accordance with the approved
details.
Reason: In order to secure an acceptable
relationship between the development and its surroundings.
23. Phasing of Development
The development
hereby approved shall be constructed in accordance with the potential phasing
plan contained within the supporting Design and Access Statement (8.1 Potential
Phasing, p53) unless otherwise agreed in writing with the Planning Authority.
Reason: In order to ensure that the affordable
housing is delivered in a timely manner.
24. Prior to the
commencement of development full details of water conservation measures to be
included within the development shall be submitted to and approved in writing
by the Planning Authority. Thereafter
the development shall be implemented with these details.
Reason: In the interests of water conservation.
(Reference: Report by Head of Development and
Economic Growth dated 7 December 2023, submitted)