Venue: on a Hybrid Basis in the McCaig Suite, Corran Halls, Oban and by Microsoft TEAMS
Contact: Karen Campbell, Senior Committee Assistant - 01631 567855
| No. | Item |
|---|---|
|
APOLOGIES FOR ABSENCE Minutes: There were no apologies intimated. |
|
|
DECLARATIONS OF INTEREST Minutes: Councillor
McKenzie declared a non-financial interest in regard to any public questions
(item 4 of these minutes) which could arise during the meeting from Mr
Strathern due to a personal connection.
She remained in the meeting but took no part in the discussion or
response to Mr Strathern’s questions. |
|
|
MINUTES |
|
|
Oban, Lorn and the Isles Area Committee - 11 March 2026 Minutes: The
Minute of the meeting of the Oban, Lorn and the Isles Area Committee, held on 11
March 2026, was approved as a correct record. |
|
|
Oban, Lorn and the Isles Area Community Planning Group - 13 May 2026 Minutes: The
Minute of the meeting of the Oban, Lorn and the Isles Area Community Planning
Group, held on 13 May 2026, was noted. |
|
|
Oban Common Good Fund - 11 May 2026 Minutes: The
Minute of the meeting of the Oban Common Good Fund, held on 11 May 2026, was
noted. |
|
|
PUBLIC QUESTION TIME - Part 1 Minutes: Mairi Malloy – Oban Community Council A sauna has been installed at the North end of Ganavan
Carpark, the Community Council has never been made aware of any planning
permission application. How did this installation
come about and by who? As no officer from the
planning department was in attendance, the question would be taken away, by the
Democratic Services Manager and a response would be sent on to Mrs Malloy
directly. Lachie Strathern Mr Strathern sought an update on the progress made
in relation to the ongoing flooding issues caused by the collapsed and blocked
drainage system leading from Crannog Lane to the main sewer. It was highlighted
that this issue had been identified in a report completed approximately two
years prior. Councillor Vennard and Councillor Lynch have also been following
up on outstanding queries on my behalf. In
response, Councillor Vennard advised that the matter had been discussed at
previous meetings, including the most recent meeting. Reference was made to an
offer by the Council to undertake remedial works on the basis of a shared cost
arrangement, whereby the relevant party would contribute half of the costs.
Councillor Vennard advised that costs would only be established should Mr
Strathern agree to accept the Council’s offer. Councillor
Lynch advised that discussions had taken place regarding the potential
costings, similar to those raised by Councillor Vennard. It was requested that
an indicative estimate of the costs be provided, noting that it was reasonable
for Mr Strathern to be informed of the likely costs prior to any agreement. Councillor
Lynch added that that Environmental Health had been contacted regarding the
matter. A response had not yet been received; however, it was confirmed that an
update would be provided directly once available. Mr
Strathern clarified that there were two separate issues which had previously
been discussed. One issue related to an incorrect connection within Mr
Strathern’s site, which he acknowledged responsibility for and confirmed his
intention to resolve independently. The
second, and primary, issue was identified as the blockage and collapse of the
main drainage system. It was noted that the previously mentioned offer of a 50%
contribution had been in relation to remedial works within Mr Strathern’s site.
However, it was emphasised that this did not address the main concern, which
remained the condition of the principal drain. As no
information could be provided by attendees at the meeting, the question would
be taken away with a response being made available to Mr Strathern. Roddy
McCuish Mr
McCuish stated that his question was in relation to Item 11 on today’s agenda,
he made reference to the committee report, which noted an allocation of £40,000
towards the project. It was observed that the wording suggested the total cost
of the bridge may vary and what anticipated costs were. He further asked for
the name of the engineering firm engaged to carry out the works, asking whether
they were Council approved as concerns had been raised by residents at the
lower end of Glencruitten Drive as installation of a
box culvert could alter the flow characteristics of the burn, potentially
affecting water speed and behaviour. Mr
McCuish also sought clarification on whether an environmental assessment had
been undertaken, given that the proposed development is situated within a
floodplain. It was emphasised that any alteration within such an area could
have significant impacts. The Chair
advised his understanding was that where a bridge involves alterations to or
spans a watercourse, approval would typically be required from SEPA. It was
agreed that officers would be asked to confirm what consents, if any, had been
granted, as these would determine the nature and extent of the works to be
undertaken. It was
indicated that responsibility for progressing the matter would lie with the
relevant department. The Chair invited officers present to respond, if able, to
the queries raised. In
response to Mr McCuish the Infrastructure Design Manager advised that the
engineering consultants used were HGA Group who were based in Inverness. She
also reported that the Infrastructure Design team would request an Approval in
Principle (AIP), within which all technical matters would require to be set out
in detail. These included hydraulic, geotechnical, and topographical surveys,
as well as the identification of relevant constraints and stakeholders involved
in the process. It was
noted that a further update would be provided in due course. Terry
Hegarty Mr
Hegarty advised that he had raised a question at a previous meeting regarding
the Mull Campus. While a response had been received promptly, he indicated that
he had not been satisfied with the content and had therefore sought further
clarification. He
reported that the subsequent clarification, received the previous day, did not
address the original query. Mr Hegarty sought guidance on how to proceed in
circumstances where he was not satisfied with the response provided, advising
that Councillors Hampsey and McKenzie had been sent the response, he received,
as they had intimated that they were interested in seeing the response to his
question. Councillor
McKenzie indicated that she had been off for a few days and had returned to a
backlog of emails to go through and unfortunately had not had the opportunity
to see the email sent by Mr Hegarty but was happy to come back to him with her
comments when she had read it. The Chair
advised that Councillor Hampsey had not yet joined the meeting but would maybe
be able to respond later, confirming that he would not respond to the email as
he disputed some of the points raised. Mr Hegarty expressed concern that the
Council’s perceived lack of engagement with community interests on these
matters could lead to a view within the community that the Council was acting
unlawfully, particularly if it did not respond to or address the concerns raised. The Chair sought advice from the Clerk on what routes would be appropriate to Mr Hegarty given that he is dissatisfied with the response he received from council officers. The Clerk advised ... view the full minutes text for item 4. |
|
|
AREA COMMITTEE QUARTERLY PERFORMANCE REPORTS – FQ4 2025/26 Report by Executive Director
with responsibility for Customer Support Services Additional documents: Minutes: The
Committee gave consideration to the Area Performance Report for financial
quarter 4 of 2025/26 (January to March 2026) which illustrated the agreed
performance measures for this period. Decision The
Oban, Lorn and the Isles Area Committee noted the performance and supporting
commentary as presented. (Reference:
Report by Executive Director with responsibility for Customer Support Services,
dated 11 May 2026, submitted) |
|
|
ARGYLL AND BUTE COUNCIL SECONDARY SCHOOLS ATTAINMENT REPORTS |
|
|
Report by Executive Director with responsibility for Education Minutes: The
Committee gave consideration to a report relating to Oban High School, which
provided information on S3 Achievement of Curriculum for Excellence Levels, attainment
in literacy and numeracy and Gaelic, National Qualifications and Insight data.
Information in relation to wider achievement qualifications; equity and
attainment and Pupil Equity Funding was also provided. Decision The
Oban, Lorn and the Isles Area Committee noted the information provided within
the report. (Reference:
Report by Executive Director with responsibility for Education dated 10 June
2026, submitted) |
|
|
Report by Executive Director with responsibility for Education Minutes: Consideration
was given to a report relating to Tiree High School which provided information on S3 ACEL
attainment in literacy and numeracy; the pass rates of national qualifications;
data from Insight Scotland; wider achievement qualifications; equity and
attainment and Pupil Equity Funding. Decision The
Oban, Lorn and the Isles Area Committee noted the information provided within
the report. (Reference: Report by Executive Director with
responsibility for Education, dated 10 June 2026, submitted) |
|
|
Tobermory High School Report by Executive Director with responsibility for Education Minutes: The
Committee gave consideration to a report relating to Tobermory High School which provided information on S3 ACEL
attainment in literacy and numeracy; the pass rates of national qualifications;
data from Insight Scotland; wider achievement qualifications; equity and
attainment and Pupil Equity Funding. Decision The
Oban, Lorn and the Isles Area Committee noted the information provided within
the report. (Reference: Report by Executive Director with
responsibility for Education, 10 June 2026, submitted) |
|
|
Report by Head of
Strategic Planning, Performance & Technology, HSCP Additional documents: Minutes: Consideration
was given to the Health and Social Care Partnership Performance (HSCP) Report
for financial quarter 3 of 2025/26 (October – December 2025). Decision The
Oban, Lorn and the Isles Area Committee - 1.
acknowledged
performance for FQ3 2025/26 (October – December) against latest
Key Performance Indicators within the Integrated Performance Management
Framework for 2025/26; 2.
noted latest Delayed
Discharge Sitrep as of 16 February 2026, as at Appendix 1 of the
report; 3.
acknowledged latest performance against the
National Health & Wellbeing Outcomes and Ministerial Steering Group
Integration Indicators, as at Appendix 2 of the report; and 4.
acknowledged
the inclusion of additional Argyll and Bute HSCP performance
metrics aligned to national reporting across Centre for
Sustainable Delivery Unscheduled Care, and the Planned
Care performance focus within the Operational Improvement Plan, as at
Appendix 3 of the report. (Reference:
Report by Head of Strategic Planning, Performance and Technology, Argyll and
Bute Health and Social Care Partnership dated 10 June 2026, submitted) |
|
|
ROADS AND INFRASTRUCTURE SERVICES UPDATE Report by Executive Director
with responsibility for Roads and Infrastructure Services Minutes: The
Committee gave consideration to a report providing links to recent activities
of Roads and Infrastructure Services. A verbal update was given to other
service ongoing projects, summer grass cutting and street cleaning programme;
ferry users group survey; trialling of messaging boards on buses; Black Lynn
Burn treatment of invasive species; the progress at Barran Landfill reduction
with 95% being diverted; proposed Soroba Road works
in summer months; street parking permits in Oban; and drainage at Crannog
Lane. An update was also provided on the
Clachan Bridge which indicated that that there are safety issues that require
detailed traffic analysis and topographical survey work to be undertaken over
the Summer. During that time there would
also be continued engagement with communities and that a report would be
brought back to the area committee in due course by way of an update. In the
meantime, it was reported that no traffic lights would be installed. Decision The
Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference:
Report by Executive Director with responsibility for Roads and Infrastructure
Services dated 20 April 2026, submitted) |
|
|
OBAN PVA FLOOD RISK MANAGEMENT UPDATE Report by Executive Director with responsibility for Roads and Infrastructure Services Minutes: The
Committee gave consideration to a report which provided an update on Flood Risk
Management within the Oban Potentially Vulnerable Area and the progress on
proposed short-medium term and medium-long term Actions. Decision The Oban, Lorn and the Isles Area Committee considered and noted the report. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure, dated June 2026, submitted) |
|
|
NORTH PIER PONTOONS - REPAIR REPORT Report by Executive Director with responsibility for Roads and Infrastructure Services Additional documents: Minutes: Consideration was given to a report noting the repairs that have been completed, future work and associated costs. Decision The Oban, Lorn and the Isles Area Committee:- 1. noted the works which have
been completed to date at the North Pier Pontoons 2. noted the works which are
required in due course and the estimated timescales for completion of the works 3. noted the confirmed and
estimated costs associated with completed and anticipated works. (Reference: Report by Executive Director with responsibility
for Roads and Infrastructure, dated May 2026, submitted)
|
|
|
DISTRIBUTION OF FUNDS - MISS AGNES ANGUS BEQUEST (UPDATE REPORT) Report by Executive Director with responsibility for Roads and Infrastructure Services Minutes: Consideration was given to an update report on the progression of the bridge works at Mossfield, the governance arrangements and design development. Decision The Oban, Lorn and the Isles Area Committee:- 1. noted the progress made in relation to the development of the Mossfield
bridge replacement project; 2. noted that design development and investigatory works are being
progressed by the Rugby Club at their own cost; and 3. noted that the allocated Bequest funding will be utilised
solely for construction of the bridge, subject to final design approval and
tender. (Reference: Report by Executive Director with responsibility for Roads
and Infrastructure, dated June 2026, submitted) |
|
|
2025/26 ACTIVE TRAVEL PROGRESS REPORT Report by Executive
Director with responsibility for Development and Economic Growth Minutes: The Committee gave consideration to a report providing an update on progress made in 2025/26 in relation to active travel projects in the Oban, Lorn and the Isles. Decision The Oban, Lorn and the Isles Area Committee:- 1. welcomed the progress made to
date across a significant number of active travel projects by the very small
Active Travel Team; 2. supported the continuation of
the projects and the submission of future funding applications to external
challenge funds to continue to develop design and construction stages to
deliver these projects; 3. supported the allocation of
the Tier 1 active travel funding element in the Council’s 26/27 block grant to
the development and delivery of appropriate active travel projects, including
those already underway in Oban, Lorn and the Isles; and 4. instructed Officers to
continue to identify and develop new active travel projects to benefit local
residents, businesses and communities. (Reference: Report by Executive Director with responsibility
for Development and Economic Growth, dated 10 May 2026, submitted) |
|
|
SUPPORTING COMMUNITIES FUND - MONITORING OF PROJECTS FUNDED Report by Chief Executive Minutes: The Committee gave consideration
to a report which highlighted the positive outcomes for communities in Oban,
Lorn and the Isles from the projects and activities funded by the Council’s
Supporting Communities Fund in 2024/25. Decision The Oban, Lorn and the Isles Area Committee:- 1.
noted and considered the positive contribution of the Supporting
Communities Fund highlighted in section 4 of this report and detailed in the
attached table; and 2.
noted that no funds have been returned. (Reference:
A report by Chief Executive, dated 10 June 2026, submitted) |
|
|
PUBLIC QUESTION TIME - Part 2 Minutes: Neil MacIntyre Mr
MacIntyre expressed concern that the allocated sum of £40,000 would be
insufficient to cover the full scope of the project at Mossfield Bridge, asking
how this could be put out to tender if there was no additional budget
identified? Mr
McCuish raised concerns similar to those previously expressed, noting that the
£40,000 allocation for the bridge project was likely to be insufficient. He
further noted that, when the initial funding had been awarded for improvements
at Mossfield, it had been stated that the bridge lay within the Mossfield
boundary. On that basis, he suggested that the bridge should appropriately form
part of the forthcoming lease application for Mossfield. The Head
of Roads and Infrastructure responded that actual costs could not be clear
until it went to the market and the tenders had
been returned showing the true cost of the works. He also noted that the £40,000 figure had been an estimate
based on the best available information and experience from previous exercises.
It was acknowledged that the final cost would not be confirmed until the tender
process had been completed. Mairi Malloy Mrs Malloy asked that following the collapse of
Carers Direct and their reported underspend, could the underspent money be used
to get more care provision on the ground? Councillor Green advised that the
Health and Social Care Partnership had received formal notification that Carers
Direct would cease trading and enter liquidation at the close of business on 1
June. Members were reassured that appropriate information sharing, risk
assessment, and continuity planning measures had been implemented. It was
confirmed that, at this stage, there was no expectation of any interruption to
essential care provision. In
relation to the underspend, it was reported that this matter had previously
been considered by the Integration Joint Board (IJB). Members were advised that
the level of underspend represented less than 1% of the IJB’s annual budget,
amounting to approximately 0.7%. It was highlighted that such an underspend is
routinely carried forward and utilised in the subsequent financial year to
support ongoing investment and service delivery. During
consideration of the following item the Chair suggested an adjournment to check
competency of potential amendments, which was agreed. On reconvening the meeting, Councillor Hume
was not present. |
|
|
NOTICE OF MOTION UNDER STANDING ORDER 13 Clachan Bridge The Oban Lorn and
Isles Area Committee: 1. Acknowledges the need for road safety improvements at the Clachan
Bridge, noting that signage alone has not proven sufficient to reduce risk to
acceptable levels. 2. Recognises that this matter has polarised the views of residents
of Seil and surrounding communities, with a lack of consensus that traffic
lights will adequately address safety issues at this location. 3. Seeks assurance, through annual update reports and a review after
3 years on the efficacy of the measures taken, to be presented to an
appropriate public committee of the Council for member endorsement. Proposed by Councillor Kieron Green Seconded by Councillor Andrew Vennard Minutes: Having
heard from the Head of Roads and Infrastructure earlier in meeting, Councillor
Green, with agreement of his seconder, moved an amended motion to reflect the
updated position regarding the Clachan Bridge. Motion The
Oban Lorn and Isles Area Committee welcomes the Clachan Bridge update provided
to members earlier in the meeting, which confirms that an options appraisal,
traffic survey, and further community engagement will be conducted prior to a
report being presented to the Area Committee in due course, and that any
decision to progress with works at the location will only happen after this. Moved
by Councillor Kieron Green, Seconded by Councillor Andrew Vennard Amendment That
the Area Committee reject the motion. Moved
by Councillor Julie McKenzie, seconded by Councillor Amanda Hampsey As
the meeting was being held on a hybrid basis, the vote required to be taken by
calling the roll and members voted as follows – Motion Amendment Councillor
Green Councillor
Hampsey Councillor
Kain Councillor
McKenzie Councillor
Lynch Councillor
Martin Councillor
Vennard Decision The
motion was carried by 5 votes to 2 and the Committee resolved accordingly. |
|
|
DRAFT OBAN, LORN AND THE ISLES AREA COMMITTEE WORKPLAN Minutes: The
Oban, Lorn and the Isles Area Committee workplan was before members for
information. Decision The
Oban, Lorn and the Isles Area Committee noted the contents of the workplan. (Reference:
Oban, Lorn and the Isles Area Committee workplan, dated 10 June 2026) |