7 CRAIGNURE STAG REPORT PDF 1 MB
Executive Director with responsibility for Roads and Infrastructure
:
Minutes:
Members gave consideration to a report which provided them with an overview of the Scottish Transport Analysis Guide (STAG) report findings; approval was sought to move to the next stage of the project.
Decision
The Argyll and Bute Harbour Board -
1. Noted the report.
2. Approved that Officers continue to engage with the local community and partners (Transport Scotland, CMAL and Calmac) to take the findings of the report forward; and
3. Approved that Officers make arrangements to move the process onto the next stage to produce an outline business case for both interim and long-term options.
(Reference: Report by Executive Director, Development and Infrastructure
dated 2 September 2019, submitted)
: