10 Helensburgh Waterfront Development Project Position Statement PDF 148 KB
Report by Executive Director with responsibility for Commercial Services
:
Minutes:
A
report providing a progress update on the delivery of the Helensburgh
Waterfront Development Project, following the abandonment of Procurement
Exercise 1 (ProcEx-1) and relaunching the Procurement Exercise (ProcEx-2) for
the main works contract, and its impact on the project programme, was before the
Committee for noting.
Decision:
The
Helensburgh and Lomond Area Committee agreed to note:
1.
the progress update for the Helensburgh Waterfront Development; and
2.
that a report will be brought to
the March 2020 meeting of the Area Committee, following completion of the
Procurement Exercise.
(Reference: Report by Executive Director with
responsibility for Commercial Services, dated 19 September 2019,
submitted.)
: