Public Question Time
:
Minutes:
Dr
Peter Brown of Helensburgh Community Council asked
the following question:-
Would the Councillors care to comment on why they are only noting the
report on the Waterfront Development despite this announcing a seven month
delay to the project caused by the council’s tendering process. Figures
in the report say that a year’s delay would increase the project cost by 1.5%.
The seven month delay therefore requires the Council to find an
additional £170,000 to address inflationary costs – this further reduces the opportunities
to provide the slide and other leisure facilities that the community clearly
desires. Instead it is just paying for what is described as a “technical
breach” in the tendering process. In real-world terms, that means a
mistake has been made, otherwise the council would not have needed to
re-tender. I would therefore ask the Councillors two questions:
Councillor Gary Mulvaney, Policy Lead for Strategic Finance and Capital
Regeneration Programme advised that the report was for noting because there was
no decision to be made by the Area Committee.
The Invitation to Tender documentation package,
which was issued by Argyll and Bute Council, was fully compliant with the
Public Contracts (Scotland) Regulations.
He
advised that he did not agree that it was a flawed bid and as noted in the
report, the issue was with respect to communications received by the Council in
connection with the procurement exercise.
Our
procurement processes must comply with the Key Principles, set out in the
Regulations:
1. Equal treatment and non-discrimination – everyone must be treated
equally and given an equal chance of winning a contract;
2. Transparency – contracting authorities must ensure that their
procurement and contracting processes are clear and transparent.
3. Proportionality – tender requirements must be set in accordance
with the needs of the contract in question
As
soon as the potential issue was identified immediate steps were taken to assess
the potential impact against the Key Principles that we have just
mentioned.
Following
specialist procurement advice from our officers and external legal advisors,
and to ensure that there was no question as to the Equality of Treatment of all
bidders, the decision was taken to abandon the procurement exercise.
In
going back out to tender we have strengthened the wording in our various
Instructions to bidders to ensure that there is no dubiety as to the
appropriate communication channels between them and us. We have also reviewed and strengthened
written guidance to our project team to ensure all guidance is strong and
robust to mitigate any chance of this happening in the re-tender process.
: