17 OBAN DEPOT RATIONALISATION PDF 203 KB
Report by Transformation Project Manager
:
Additional documents:
Minutes:
The Committee gave consideration to a report advising of the progress regarding the Oban Depot
Rationalisation Project. The project had reached a significant milestone with
the recent appointment of Luddon Construction as the Council’s contractor, on a
design and build basis.
Decision
The
Oban, Lorn and the Isles Area Committee noted the
contents of the report.
(Ref:
Report by Transformation Project Manager dated 13 February 2019, submitted)
: