Minutes:

The Committee considered a progress update report on the delivery of the Helensburgh Waterfront Development Project, including the following matters: RIBA Stage 4 – Technical Design; Procurement of the Main Works Contract; Development of the Full Business Case; Programme for delivering the project; and the Planning Application.

 

Decision

 

The Helensburgh and Lomond Area Committee:

 

1.     Noted the progress update contained in the report; and

 

2.    Agreed to recommend to the Policy and Resources Committee that an allowance should be made for additional funding, as set out at Section 5.6 of the Report, as part of the 2019-2020 Budget Process, for the two additional sections of public realm improvements approved for inclusion at the end of Stage 3.

 