Issue - meetings

Tarbert and Lochgilphead Regeneration Fund - TO FOLLOW

Meeting: 06/12/2017 - Mid Argyll, Kintyre & the Islands Area Committee (Item 12)

12 Tarbert and Lochgilphead Regeneration Fund pdf icon PDF 495 KB

Report by Executive Director of Development and Infrastructure Services

:

Minutes:

A report providing an update on the proposals for the Gleaner Phase 1 project and the full business case, was considered.

 

Decision

 

The Committee agreed to recommend to the Policy and Resources Committee that:

 

  1. The maximum grant funding of up to £250,000 should be allocated to the Gleaner Phase 1 from the Tarbert and Lochgilphead Regeneration Fund; and
  2. Delegated authority to the Executive Director of Development and Infrastructure Services to confirm the final grant amount.  The Executive Director will only have the delegated authority to approve grant where it would not exceed the contribution made by Scottish Canals/Scottish Waterways Trust.

 

(Ref:  Report by Senior Development Officer dated 7th November 2017, submitted).

: