This application was considered at a discretionary hearing on 17 June 2024 where the Committee agreed to continue consideration to allow Members to seek advice of Officers on the preparation of a competent Motion.
It was noted that only those Members present today that attended the discretionary hearing could take part in the determination of the application.
Councillors John Armour and Audrey Forrest left the meeting at this point.
Motion
To agree that the AMSC permission be approved as per
Officer recommendation within the main report, with the minor correction that
the referenced drainage strategy within the approved supporting documents is
amended to the Issue 5 drainage strategy submission dated 10.6.24.
Moved by Councillor Gordon Blair, seconded by Councillor Liz McCabe.
Amendment
The Planning, Protective Services and Licensing Committee;
· Notes that satisfactory operation of the
proposed drainage scheme relies on attenuation provided by an existing pond
located on third party land to the south-west of the application site.
· Considers the pond is an integral component
of the overall drainage solution for the site as water discharged from the
development will pass through this existing water feature prior to entering the
Geilston Burn.
· Recognises that the developer has put forward
a competent Surface Water Drainage (SuDS) Scheme, as required by condition 12,
but further notes that the proposal also includes for the redirection and the
discharge of unattenuated surface water flow from the existing housing
development at Kilmahew Avenue, Grove and Court into this pond that will
increase flows into the pond.
· Finds that insufficient technical details
have been submitted to confirm the attenuation properties of the pond and its
capacity to accommodate the additional surface water discharge.
· Finds that insufficient technical details
have been submitted to demonstrate that the proposed drainage scheme will not
give rise to unacceptable harm through flooding to the residential property
known as ‘The Glen’ should the combined discharges lead to the pond overtopping
its sidewalls.
· Therefore finds that condition 11 has not
been satisfied, and consequently refuses the Approval of Matters the subject of
Conditions (AMSC) permission.
Moved by Councillor Kieron Green, seconded by Councillor Paul Kennedy.
A vote was taken by calling the roll.
Motion Amendment
Councillor Blair Councillor Brown
Councillor Kain Councillor Green
Councillor McCabe Councillor Hardie
Councillor Wallace Councillor Howard
Councillor Kennedy
The Amendment was carried by 5 votes to 4 and the Committee resolved accordingly.
Decision
The Planning, Protective Services and Licensing Committee;
· Noted that satisfactory operation of the
proposed drainage scheme relied on attenuation provided by an existing pond
located on third party land to the south-west of the application site.
· Considered the pond was an integral component
of the overall drainage solution for the site as water discharged from the
development would pass through this existing water feature prior to entering
the Geilston Burn.
· Recognised that the developer had put forward
a competent Surface Water Drainage (SuDS) Scheme, as required by condition 12,
but further noted that the proposal also included for the redirection and the
discharge of unattenuated surface water flow from the existing housing
development at Kilmahew Avenue, Grove and Court into this pond that would
increase flows into the pond.
· Found that insufficient technical details had
been submitted to confirm the attenuation properties of the pond and its
capacity to accommodate the additional surface water discharge.
· Found that insufficient technical details had
been submitted to demonstrate that the proposed drainage scheme would not give
rise to unacceptable harm through flooding to the residential property known as
‘The Glen’ should the combined discharges lead to the pond overtopping its
sidewalls.
· Therefore found that condition 11 had not
been satisfied, and consequently refused the Approval of Matters the subject of
Conditions (AMSC) permission.
(Reference: Report by Head of Development and Economic Growth dated 7 March 2024 and supplementary report number 1 dated 13 June 2024, submitted)
: