CAMPBELTOWN FLOOD PROTECTION SCHEME

Meeting: 02/09/2021 - Environment, Development and Infrastructure Committee (Item 9)

9 CAMPBELTOWN FLOOD PROTECTION SCHEME pdf icon PDF 213 KB

Report by Executive Director with responsibility for Roads and Infrastructure

:

Minutes:

The Committee gave consideration to a report providing an update on the progress with the Campbeltown Flood Protection Scheme including work completed, key dates and risks going forward.

 

Decision

 

The Environment, Development and Infrastructure Committee –

 

1.    Endorsed the content of the submitted report.

 

2.    Noted that the full Business Case would be brought back to the Environment, Development and Infrastructure Committee in December 2021.

 

3.    Noted that construction of the final scheme would be subject to approval of Full Business Case prior to tender award.

 

(Reference:  Report by Executive Director with responsibility for Roads and Infrastructure dated 2 September 2021, submitted)

 

: