Budget Monitoring as at 31 July 2021 - TO FOLLOW

Meeting: 15/09/2021 - Argyll and Bute HSCP Integration Joint Board (IJB) (Item 10)

10 Budget Monitoring - 4 months to 31 July 2021 pdf icon PDF 336 KB

Report by Head of Finance and Transformation

:

Additional documents:

Minutes:

The Board gave consideration to a report providing a summary of the financial position of the Health and Social Care Partnership as at 31 July 2021 and an updated financial forecast for the year.

 

Decision

 

The Integration Joint Board –

 

1.    Noted that the P4 forecast outturn position is a forecast overspend of £1.4m.

 

2.    Noted that subsequent analysis and modelling of Social Work Forecasts had reduced the forecast overspend to £0.8m.

 

3.    Noted that actions were currently being progressed to manage spend and recover the position by the year end.

 

4.    Noted that there was a year to date overspend of £0.1m as at 31 July 2021.

 

5.    Noted the Financial Risks analysis for 2021/22.

 

(Reference:  Report by Head of Finance and Transformation dated 15 September 2021, submitted)

 

: