The Board gave consideration to a report providing a summary of the financial position of the Health and Social Care Partnership as at 31 July 2020.  The report noted that there was still considerable uncertainty around the financial impact of the Covid-19 pandemic.

 

Decision

 

The Integration Joint Board –

 

1.    Noted that the forecast outturn position for 2020-21 was a forecast overspend of £2.964m as at 31 July 2020 and that there was a year to date overspend of £2.117m as at the same date. 

 

2.    Noted the above position excluded any provision for Scottish Government assistance with non-delivery of savings due to Covid-19, or for the on-going dispute with NHS Greater Glasgow & Clyde.

 

3.    Approved the proposed settlement of the dispute with NHS Greater Glasgow and Clyde as set out at paragraph 3.4.2.

 