HELENSBURGH WASTE TRANSFER STATION PROJECT UPDATE

Decision Maker: Environment, Development and Infrastructure Committee, Policy and Resources Committee

Is Key decision?: No

Is subject to call in?: No

Decisions:

The Committee gave consideration to a report providing an update on the Helensburgh Waste Transfer Station project following the completion of the Options Appraisal and making a recommendation in relation to the next steps for this project and associated budgets.

 

Decision

 

The Environment, Development and Infrastructure Committee –

 

1.    noted that the proposed Helensburgh Waste Transfer Station no longer provided the optimum solution to ensure Biodegradable Municipal Waste compliant disposal arrangements in the Helensburgh and Lomond area;

 

2.    agreed that officers should not progress further with the development and delivery of the Helensburgh Waste Transfer Station Project;

 

3.    recommended to the Policy and Resources Committee that the remainder of the £3m of budget earmarked for this project be retained to support other funding related pressures within the waste service; and

 

4.    noted that should circumstances change, specifically the cost benefit ration, that the scheme could be revisited.

 

(Reference: Report by Executive Director with responsibility for Roads and Infrastructure Services dated February 2025, submitted)

Publication date: 24/03/2025

Date of decision: 20/03/2025

Decided at meeting: 20/03/2025 - Environment, Development and Infrastructure Committee