Decision Maker: Environment, Development and Infrastructure Committee, Policy and Resources Committee
Is Key decision?: No
Is subject to call in?: No
The Committee gave consideration to a report providing an update on the Helensburgh Waste Transfer Station project following the completion of the Options Appraisal and making a recommendation in relation to the next steps for this project and associated budgets.
Decision
The Environment, Development and Infrastructure Committee –
1. noted that the proposed Helensburgh Waste Transfer Station no longer provided the optimum solution to ensure Biodegradable Municipal Waste compliant disposal arrangements in the Helensburgh and Lomond area;
2. agreed that officers should not progress further with the development and delivery of the Helensburgh Waste Transfer Station Project;
3. recommended to the Policy and Resources Committee that the remainder of the £3m of budget earmarked for this project be retained to support other funding related pressures within the waste service; and
4. noted that should circumstances change, specifically the cost benefit ration, that the scheme could be revisited.
(Reference: Report by Executive Director with responsibility for Roads and Infrastructure Services dated February 2025, submitted)
Publication date: 24/03/2025
Date of decision: 20/03/2025
Decided at meeting: 20/03/2025 - Environment, Development and Infrastructure Committee