Decision Maker: Policy and Resources Committee
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
The Committee gave consideration to a report requesting agreement on
additional funding being allocated to Campbeltown War
Memorial and permission for Argyll Countryside Trust (ACT) to sell their Eco-Hub
which had been part funded through Crown Estates Funding.
Decision
The Policy and Resources Committee agreed to –
1.
allocate
additional funding of up to £11,000 to complete the upgrade works at Campbeltown War Memorial from Crown Estate contingency
funding; and
2.
grant
permission to ACT to sell their Eco-Hub, which was part funded through Crown
Estates funding in 2021; and agree in principal that the returned proceeds in
addition to the remaining 5% retention (anticipated to be £28.5k) are reinvested
in the new Kilmory site.
(Reference: Report by Executive Director with responsibility for
Development and Economic Growth dated 26 November 2024, submitted)
Publication date: 06/12/2024
Date of decision: 05/12/2024
Decided at meeting: 05/12/2024 - Policy and Resources Committee
Accompanying Documents: