The Committee considered a report providing an update on the Rural
Growth Deal (RGD) and specifically costs associated with the Business Case and
Project Development.
Decision
The Policy and Resources Committee –
1.
noted that
the total estimated essential development costs to inform Treasury Five
compliant Full Business Cases for all projects amounted to £3.183m and these
costs required to be incurred in advance of Central Government endorsement at
risk to the Council and lead delivery partners;
2.
agreed that
the Council sets aside a fund from the Priorities Investment Fund to the value
of £0.700m that can pay for the development costs for Council projects on the
basis that all will be paid back by the end of Year 10;
3.
agreed that
any cash flow funding requests for projects led by external partners would be
brought to the Policy and Resources Committee for approval as and when a
request for funding was made and considered on a case by case basis; and
4.
delegated to
the Internal Programme Board (Chief Executive and Executive Directors) to
approve pre-development funding requests relating to Council led projects up to
a threshold of £250k per project from the new Fund.
(Reference: Report by Executive Director with responsibility for
Development and Economic Growth dated 20 November 2024, submitted)
Publication date: 06/12/2024
Date of decision: 05/12/2024
Decided at meeting: 05/12/2024 - Policy and Resources Committee
Accompanying Documents: