Decision Maker: Policy and Resources Committee
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
The Committee considered a report updating them on progress in the delivery of the Lorn Arc Tax Incremental Financing Programme and its nine capital infrastructure investment projects.
Decision
The Committee –
1. Noted the current progress with the Lorn Arc Programme;
2. Noted that recruitment is underway for 1 full time Lorn Arc Programme Manager, 1 full time Lorn
Arc Project Manager and a Secondment opportunity for a Lorn
Arc Project Manager;
3. Approved Officers formally requesting from the Lorn Arc TIF Executive the removal of the two Barcaldine
projects from the Lorn Arc Business Case but
retaining the option to borrow up to £18.9m across the remaining projects or
bringing forward additional projects in due course subject to approval and
affordability.
4. Approved revising the reporting Tolerance levels in
line with the levels set for the Council’s monthly Capital Financial Reporting
i.e. Project Plan +/- 2 months on agreed completion and Project Budget +/- 5%
of agreed budget subject to a minimum of £50,000.
(Reference: Report by Executive
Director – Development and Infrastructure Services dated 16 February 2016,
submitted)
Publication date: 23/03/2016
Date of decision: 17/03/2016
Decided at meeting: 17/03/2016 - Policy and Resources Committee