Is Key decision?: No
Is subject to call in?: No
The Committee agreed to recommend to the Policy and Resources Committee that the Council –
1. Progresses with
an innovative lighting energy efficient scheme as detailed in this business
case, the costs of which are summarised in 5.4 of this report, in order to
reduce future cost pressure relating to street lighting electricity.
2. Agrees to a
tender process being completed and that the energy efficient scheme is
progressed utilising the most cost effective model as determined from the
tender process.
3. Agrees that
the remaining reduced electricity budget, as a result of the innovative
lighting scheme, is inflated in line with energy costs on an annual basis.
4. Agrees that
the balance of savings generated is used to fund a column replacement program
with replacements being prioritised on condition.
Publication date: 18/11/2015
Date of decision: 12/11/2015
Decided at meeting: 12/11/2015 - Environment, Development and Infrastructure Committee