Decision Maker: Environment, Development and Infrastructure Committee
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
The Committee gave consideration to a report providing an update on the
progress towards a permanent repair of the A816 at Ardfern
which was damaged during the severe weather event in October 2023.
Decision
The Environment, Development and Infrastructure Committee:
1.
agreed
that the existing budget allocation of £1.1m be used to progress the next phase
of detailed business case development required to provide a recommended option
with a further and more highly developed budget estimate and outline delivery
programme; and
2.
noted
the difference in the current cost estimate and that originally produced and
reported to Members in February 2024 and the reasons for this set out in the
body of the report.
(Reference: Report by Executive Director with responsibility for Roads
and Infrastructure Services dated September 2025, submitted)
Publication date: 15/09/2025
Date of decision: 11/09/2025
Decided at meeting: 11/09/2025 - Environment, Development and Infrastructure Committee
Accompanying Documents: