Decision Maker: Policy and Resources Committee
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
The Committee gave consideration to a report advising that the Place Based Investment Programme Offer of Grant from Scottish Government had been received on 25 June 2025 and had confirmed partial release of funding resulting in a reduction from £496,000 to £388,368, with the remaining £107,632 subject to the Scottish budget position later in the year.
Decision
The Policy and Resources Committee agreed to the reprioritisation of projects set out in Table 1, paragraph 3.2 of the submitted report following Scottish Government notification that this funding would now be received in two tranches.
(Reference: Report by Executive Director with responsibility for Development and Economic Growth dated 1 July 2025, submitted)
Publication date: 26/08/2025
Date of decision: 21/08/2025
Decided at meeting: 21/08/2025 - Policy and Resources Committee
Accompanying Documents: