Decision Maker: Environment, Development and Infrastructure Committee
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
The Committee gave consideration
to a report providing detail of the proposed Footway Reconstruction Programme
for 2023/24. A budget of £750,000 had been allocated as part of the 2023 budget
process and the report advised of how this had been allocated across the four
administrative areas based on the percentage of footways in each area.
Decisions
The Environment, Development and
Infrastructure Committee –
1. endorsed the proposed programme of
capital works for 2023/24; and
2.
agreed that details of each Area Committee’s programme would be
forwarded on to individual Elected Members.
(Reference: Report by Executive Director with responsibility for Roads and Infrastructure Services dated July 2023, submitted)
Publication date: 04/09/2023
Date of decision: 31/08/2023
Decided at meeting: 31/08/2023 - Environment, Development and Infrastructure Committee
Accompanying Documents: