Decision Maker: Argyll and Bute Council
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
The
Council gave consideration to a report providing an update on the Scottish Government’s recent announcement on
the long term solution for the Rest and Be Thankful. The preferred option was for a debris flow
shelter along the line of the existing Trunk Road with a construction time of
three to four years following improvements to the Old Military Road. This had been considered the most deliverable
option by Transport Scotland.
Decision
The
Council agreed to –
1.
request
that the Leader of the Council writes to the newly appointed Minister for
Transport, Fiona Hyslop MSP, to highlight our
communities’ concerns and their need for urgency in progressing the permanent
solution for the Rest;
2.
seek
reassurance from the Minister and her officials at Transport Scotland on a
range of points including clear timescales; measures to mitigate against delay;
contingency plans for maintaining access in the event of a major incident
during construction; and confirmation that the A82 upgrade will progress as
planned;
3.
ask the
Minister to convene an urgent meeting of the A83 Taskforce given the commitment
made at the last meeting in Arrochar, in the context
of this recent announcement and the questions that remain within the community
and local industry;
4.
call upon
the Minister to ensure that the Scottish Government, Transport Scotland and any
other relevant agency will prepare and share a robust communications strategy
which will reinforce the vital message at a national level that Argyll and Bute
is open for business;
5.
reiterate
this Council’s longstanding position that urgent completion of the permanent
solution is of the utmost importance in order that Argyll and Bute’s current
and future opportunities for population and economic growth are not
compromised; and
6.
request
officers to respond to the Scottish Government’s recent announcement on the
basis of paragraphs 1 to 5, above.
(Reference:
Report by Executive Director with responsibility for Roads and
Infrastructure Services dated June 2023, submitted)
Publication date: 29/06/2023
Date of decision: 29/06/2023
Decided at meeting: 29/06/2023 - Argyll and Bute Council
Accompanying Documents: