The Committee gave consideration to a report providing an update on the wider Lorn Arc Programme and the current live Lorn Arc projects at Dunbeg and Oban Airport.
Decision
The Policy and Resources Committee
noted the progress with
the Lorn Arc Project, particularly –
1.
ongoing
discussions with Scottish Government to amend the TIF agreement;
2.
anticipated
submissions of full planning applications for Dunbeg
Corridor in early 2023; and
3.
ongoing
work to prepare a Business Case for investment in a Headquarters building at
Oban Airport.
(Reference:
Report by Executive Director with responsibility for Development and
Economic Growth dated 2 November 2022, submitted)