Decision details

PLAY PARK FUNDING

Decision Maker: Environment, Development and Infrastructure Committee

Decision status: For Determination

Is Key decision?: No

Is subject to call in?: No

Decisions:

The Committee gave consideration to a report providing an update on the 5 year budget for play park equipment allocated to Argyll and Bute Council by Scottish Government from 2021/22.  The report outlined the engagement officers had had locally through Youth Forums and proposed a further consultation approach.

 

Decision

 

The Environment, Development and Infrastructure Committee –

 

1.    noted the available funding for play park equipment as detailed in the submitted report;

 

2.    agreed the budget split for each of the 4 administration areas as outlined in Appendix 1 to the submitted report; and

 

3.    noted the proposed further proposed further engagement with other groups, including Youth Forums and relevant Community Councils, and that a report outlining the process and timelines would be brought to the Environment, Development and Infrastructure Committee in March 2023. 

 

(Reference:  Report by Executive Director with responsibility for Roads and Infrastructure Services dated  November 2022, submitted)

 

Publication date: 05/12/2022

Date of decision: 01/12/2022

Decided at meeting: 01/12/2022 - Environment, Development and Infrastructure Committee

Accompanying Documents: