Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
The Council considered a report which updated members on progress in relation to the refurbishment of 6 properties on the island of Ulva by the North West Mull Community Woodland Company and requested an additional Strategic Housing Fund payment to enable the delivery of the 6 affordable houses on the island of Ulva.
Decision
The Council approved the sum of £90,663 from the Strategic Housing Fund. This is in addition to the £12,000 per unit £72,000 in total, Officer mandate already approved from the SHF for this project.
(Ref: Report by Executive Director with responsibility for Development and Economic Growth dated 30 June 2022, submitted)
Publication date: 06/07/2022
Date of decision: 30/06/2022
Decided at meeting: 30/06/2022 - Argyll and Bute Council
Accompanying Documents: