Decision Maker: Policy and Resources Committee
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
The Committee gave consideration to a report providing an update on the Lorn Arc initiative. The report dealt with proposed amendments to the Tax Incremental Finance Agreement (TIF) between the Council and the Scottish Government. The report provided detailed updates on the current live projects at Dunbeg and Oban Airport.
Decision
The Policy and Resources Committee –
1.
Noted and endorsed that
officers would continue to negotiate with Scottish Government to seek extension
of the TIF project completion and debt repayment deadlines.
2.
Noted the progress made
relating to Dunbeg Gateway Features and Halfway House
Roundabout.
3.
Agreed that officers
would develop a business case for further Council investment at the Oban
Airport Business Park site for the development of a new headquarters office /
hanger building to be leased on completion to TSL Contractors Limited (TSL)
including utilising the remainder of funding previously approved by the P&R
Committee for Oban Airport Business Park.
4.
Agreed that officers
would continue to progress with the other innovative proposals for the Oban
Airport Business Park while the funding and tender bids were awaiting
conclusion.
5.
Noted that TSL would concurrently
progress with the planning process in respect of the proposed development.
6.
Noted the
re-establishment of the Dunbeg Corridor Working Group
that had held its first meeting with key stakeholders.
(Reference:
Report by Executive Director with responsibility for Development and
Economic Growth dated 18 January 2022, submitted)
Publication date: 22/02/2022
Date of decision: 17/02/2022
Decided at meeting: 17/02/2022 - Policy and Resources Committee