The Committee gave consideration to a report providing an update on the progress with the Campbeltown Flood Protection Scheme, including the funding position and making recommendations in order for the project to progress.

 

Decision

 

The Environment, Development and Infrastructure Committee –

 

1.    Approved the invitation to tender for the construction of the main flood scheme and supply and installation of property flood resilience measures.

 

2.    Noted that a paper detailing the full Business Case would be brought back to the Committee in September 2021.  Construction of the final scheme would be subject to approval of Full Business Case prior to tender award.

 

(Reference:  Report by Executive Director with responsibility for Roads and Infrastructure dated 10 May 2021, submitted)

Publication date: 08/06/2021

Date of decision: 03/06/2021

Decided at meeting: 03/06/2021 - Environment, Development and Infrastructure Committee