Decision Maker: Oban Lorn & The Isles Area Committee
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
The Committee gave consideration to a report which presented the final step in the community festive lighting handover in Oban, Lorn and the Isles with the proposed allocation of the remaining festive funds.
Decision
The Oban, Lorn and the Isles Area Committee;
1. endorsed the significant amount of work undertaken by the Council’s streetlighting team in developing community handover arrangements in Oban, Lorn and the Isles; and
2. agreed the allocation of remaining funds of £10,100 as set out at in the table below;
Town/village |
Funding available |
Oban |
7,390 |
Tobermory |
2,710 |
TOTAL |
10,100 |
(Reference: Report by Executive Director with responsibility for Roads and Infrastructure dated 16 August 2019, submitted)
Publication date: 18/09/2019
Date of decision: 11/09/2019
Decided at meeting: 11/09/2019 - Oban Lorn & The Isles Area Committee
Accompanying Documents: