The Committee gave consideration to a report which presented the final step in the community festive lighting handover in Bute and Cowal with the proposed allocation of the remaining festive funds.

 

Decision

 

The Bute and Cowal Area Committee;

 

1.    thanked the Project Manager for his hard work and effort put into the project;

 

2.    endorsed the significant amount of work undertaken by the Council’s street lighting team in developing community handover arrangements in Bute and Cowal; and

 

3.    agreed the allocation of remaining funds of £11,557 as set out in the table below;

 

Town/village

Funding available

Dunoon

6,807

Rothesay

2764

Innellan

662

Sandbank

662

Port Bannatyne

662

TOTAL

11,557

 

(Reference: Report by Executive Director with responsibility for Roads and Infrastructure Services dated 7 August 2019, submitted)