The Policy and Resources Committee gave consideration to a recommendation from the Mid Argyll, Kintyre and the Islands Area Committee held on 6 December 2017 in respect of the Tarbert and Lochgilphead Regeneration Fund – Gleaner Phase 1 Full Business Case.

 

Decision

 

The Committee agreed to:

 

1.     The maximum grant funding of up to £250,000 should be allocated to the Gleaner Phase 1 from the Tarbert and Lochgilphead Regeneration Fund; and

 

2.     Delegated authority to the Executive Director of Development and Infrastructure Services to confirm the final grant amount.  The Executive Director will only have the delegated authority to approve grant where it would not exceed the contribution made by Scottish Canals/Scottish Waterways Trust.

 

(Reference:  Recommendation by Mid Argyll, Kintyre and the Islands Area Committee held on 6 December 2017 and report by Executive Director – Development and Infrastructure Services dated 7 November 2017, submitted)

Publication date: 18/12/2017

Date of decision: 08/12/2017

Decided at meeting: 08/12/2017 - Policy and Resources Committee