Decision Maker: Policy and Resources Committee
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
Consideration was given to a report which requested the Council to approve an additional financial underwriting of the Pavilion project of £1M following the return of tenders and a subsequent value engineering exercise.
Decision
The Policy and Resources Committee –
1. Noted that the Rothesay pavilion Adaptive Restoration and Extension Works Contract has been the subject of a competitive procurement exercise involving four tenderers.
2. Noted that following the receipt of tenders a rigorous Value Engineering Exercise was required to reduce costs.
3. Noted that following the completion of the Value Engineering Exercise a funding shortfall remained.
4. Agreed to recommend to Council that an additional financial underwriting of £1M be taken from the unallocated general fund which increases total underwriting to £3, 620,000 taking the Council’s maximum contribution to £5,689,000.
5. Noted that discussions are ongoing with key funding partners with a view to applying for additional funds, where possible.
(Reference: Report by Executive Director – Development and Infrastructure Services dated 2 June 2017, submitted)
Publication date: 03/07/2017
Date of decision: 29/06/2017
Decided at meeting: 29/06/2017 - Policy and Resources Committee
Accompanying Documents: