HIGHLIGHT / PROGRESS REPORT Helensburgh CHORD

Meeting: 09/12/2014 - Helensburgh & Lomond Area Committee (Item 17)

HIGHLIGHT / PROGRESS REPORT Helensburgh CHORD

Report by Executive Director -  Development and Infrastructure.

:

Additional documents:

Minutes:

The Committee considered a report which provided an update on progress for the  Helensburgh CHORD project for the period 22 September – 12 November 2014.

 

Discussion followed and Members raised the issue of parking bay widths in Sinclair Street and clarification was sought in regards the ability to maintain enforcement charges.  The CHORD Programme Manager affirmed that the parking bay width met National Design Standards and enforcement charges could be effectively implemented.   

 

Decision

 

Members agreed to note the report.

 