4 NORTH PIER MARITIME VISITOR FACILITY PDF 94 KB
Covering Report (pg 75-80)
Annex 1.1 (pg 81-114)
Annex 1.2 (pg 115-120)
E2 Annex 1.3 (pg 121)
Reports by Oban Regeneration Project Manager
:
Additional documents:
Minutes:
A report updating the Committee on the concept design for
the North Pier Maritime Visitor Facility was considered.
The report explains the design process and options
considered prior to making a final recommendation of a concept design that
meets the terms of the initial brief, can be provided within our tight budget
parameters, can be delivered by 2014-2016 and offers flexibility for longer
term strategic/regeneration projects in the wider Oban area.
Decision
The Committee:
- Agreed
to the consultants moving forward with the recommended concept design –
option 5 in the report, to detailed design stage (RIBA Stage 3);
- Agreed
to the consultants carrying out more detailed design and technical work
than would normally be required at this stage whilst the overall approved
design fee, to enhance the full business case, reduce the risks associated
with the next stage of the project and allow for an earlier construction
start;
- Agreed
to programming option 2 as this allows for the earliest delivery of the
project, with demolition of the White Building in January 2015 – August
2015, assuming approaches of a full Business Case in September 2014;
- Noted
that a planning application will be submitted for the detailed design
during June 2014 to allow for a full Business Case to be brought to the
Area Committee/Business Day and Full Council during September 2014; and
- Agreed
to hold a Special Area Committee in advance of the Business Day on 10th
September 2014 to consider the full Business Case.
(Ref: Report by Oban
Regeneration Project Manager dated 13th March 2014, submitted).
: